Cubic yards - Study guides, Class notes & Summaries
Looking for the best study guides, study notes and summaries about Cubic yards? On this page you'll find 536 study documents about Cubic yards.
All 536 results
Sort by
-
ACI Flatwork Exam All Possible Questions and Answers with complete solution
- Exam (elaborations) • 9 pages • 2024
- Available in package deal
-
- $7.99
- 2x sold
- + learn more
It is important that the ____________ __________ read and understand project specifications. - 
Answer-finisher foreman 
If the crew can place and finish 100 yd3 of concrete per hour, the producer's delivery rate should be 
about _____ yd3 per hour. - Answer-100 
Concrete is sold by the ton? - Answer-False 
Delays in discharging concrete trucks can result in the concrete being hard to: - Answer-pump, place, 
and finish 
When there is room for two concrete trucks ready to discharge into a pump ho...
-
OSSF TEST PRACTICE EXAM AND QUALITY ANSWERS 2024.
- Exam (elaborations) • 14 pages • 2024 Popular
-
Available in package deal
-
- $8.19
- 1x sold
- + learn more
_______ and ________ soil textural classes are always unsuitable for standard absorptive OSSF - Answer class IA and IV 
 
List each of the major soil horizons - Answer surface soil A, surface soil B, and parent material 
 
_____________ is a term describing the ability of water to migrate through a soil profile under either _________ or __________ conditions. - Answer Hydraulic conductivity, saturated, unsaturated 
 
Interconnected pores in the soil profile allow ______ and _______ to ente...
-
OSSF DR TEST PRACTICE QUESTIONS WITH VERIFIED ANSWERS
- Exam (elaborations) • 24 pages • 2024
- Available in package deal
-
- $9.99
- 1x sold
- + learn more
OSSF DR TEST PRACTICE QUESTIONS 
 
WITH VERIFIED ANSWERS 
 
_______ and ________ soil textural classes are always unsuitable for standard absorptive OSSF 
class IA and IV 
 
List each of the major soil horizons surface soil A, surface soil B, and parent material 
 
_____________ is a term describing the ability of water to migrate through a soil profile under 
either _________ or __________ conditions. Hydraulic conductivity, saturated, unsaturated 
 
Interconnected pores in the soil profile all...
-
Michigan Builders License Exam Questions With Correct Answers
- Exam (elaborations) • 71 pages • 2023
- Available in package deal
-
- $13.49
- 7x sold
- + learn more
Created to serve as a complete, comprehensive code regulating the construction of single-family, two-family and buildings consisting of three or more townhouse units. - Answer IRC (International Residential Code) 
 
Administrative - Answer First 2 chapters of code book are 
 
True - Answer Plans or supporting documents are almost always required by the controlling authority prior to issuing a permit. T or F 
 
Yes - Answer Does the building official have the authority to render interpretations o...
-
Study Guide for Massachusetts 1C Hoisting License Questions and Correct Answers 100%
- Exam (elaborations) • 15 pages • 2024
-
- $14.99
- + learn more
Study Guide for Massachusetts 1C 
Hoisting License Questions and Correct 
Answers 100% 
WHAT DO YOU NEED TO INSPECT? - CORRECT ANSWER-ROPES 
CABLES 
CLUTCHES 
CHAINS AND BEARINGS 
GEARS AND ALL OTHER PARTS SUBJECT TO WEAR 
INPECTION FORMS - CORRECT ANSWER-SHOULD BE FILLED OUT AND KEPT 
ON FILE FOR THE LIFE OF THE MACHINE 
SHOULD BE INSPECTED DAILY OR AT EVERY SHIFT OR EVERY 30 DAYS 
CUBIC YARDS - CORRECT ANSWER-A STANDARD WHEELBARROW: 
1 CUBIC YARD 
TRI AXEL DUMP TRUCKS: 
APROX. 18 CUBIC Y...
And that's how you make extra money
-
Michigan Residential Builder's License Test With Correct Solution
- Exam (elaborations) • 114 pages • 2023
- Available in package deal
-
- $11.49
- 2x sold
- + learn more
What is the 1st offense penalty for engaging in the practice of residential building without a license? - Answer Not less than $5K and not more than $25K and/or 1 year 
 
What is the penalty for engaging in the practice of residential building, resulting in a death? - Answer Not less than $5K and not more than $50K and/or 4 years 
 
On your individual builder's license application, what should you write as your "business address"? - Answer Your personal address 
 
What is the cost of the indi...
-
AIC Exam Questions And Answers (Verified And Updated)
- Exam (elaborations) • 48 pages • 2024
-
- $11.49
- + learn more
AIC Exam Questions And Answers (Verified And Updated) 
1. A project schedule has been updated. The activity placement of spread footing concrete was originally scheduled to begin as early as day 10. The activity duration is 4 days. The actual start day was day 12. The original schedule had calculated total float of 7 days for this activity. The recalculated total float for the activity, when updated, would be... 
A. 2 days 
B. 5 days 
C. 6 days 
D. 9 days 
B. 5 Days 
 
 
2. The purpose of retain...
-
CSLB General B Practice Questions & Answers #1 Exam Review 2024-2025
- Exam (elaborations) • 22 pages • 2024
- Available in package deal
-
- $15.99
- + learn more
CSLB General B Practice Questions & Answers #1 
Exam Review 
1 / 22 
1. It is better to use a leveling rod than a 
yard stick when using a transit because 
the rod is: 
A. Straighter 
B. Longer 
C. Easier to read 
D. Graduated to 64 h 
1. Fill dirt is measured in: 
A. Cubic yards 
B. Square yards 
C. Cubic feet 
D.Square feet 
1. What backfill should be used after concrete forms have been removed?
-
AIC Exam Final Questions & Answers 2024/2025
- Exam (elaborations) • 31 pages • 2024
-
Available in package deal
-
- $10.99
- + learn more
AIC Exam Final Questions & Answers 2024/2025 
 
 
5 days - ANSWERSA project schedule has been updated. The activity placement of spread footing concrete was originally scheduled to begin as early as day 10. The activity duration is 4 days. The actual start day was day 12. The original schedule had calculated total float of 7 days for this activity. The recalculated total float for the activity, when updated, would be 
 
a. 2 days b. 5 days c. 6 days d. 9 days 
 
Complete project per contract - A...
-
ACI 318-14 Concrete Code Questions and Answers 100% Pass
- Exam (elaborations) • 11 pages • 2024
- Available in package deal
-
- $9.99
- + learn more
ACI 318-14 Concrete Code Questions 
 
and Answers 100% Pass 
 
1 - What is the minimum thickness of concrete bearing walls? 
 
1 - 5 1⁄2 inches 
2 - 6 inches 
3 - 7 1⁄2 inches 
 
4 - 8 inches 1 - 5 1⁄2 inches 
 
2 - What is the maximum amount of fly ash that can be added to concrete exposed to deicing 
chemicals? 
 
1 - 10% 
2 - 25% 
 
3 - 30% 
 
4 - 50% 2 - 25% 
 
3 - You are doing a concrete placement of 750 cubic yards. How many strength tests will be 
needed? 
 
1 - Two 
 
2 - Four 
3 ...