NERC
Liberty University
Page 2 out of 27 results
Sort by
-
NERC RC TEST 64 QUESTIONS WITH COMPLETE SOLUTIONS
- Exam (elaborations) • 4 pages • 2022
-
Available in package deal
-
- $5.49
- 1x sold
- + learn more
System studies identify what correct answer: Predict operations and identify constraints 
 
If ACE remains the same and frequency goes up what has happened? correct answer: Someone lost load 
 
When a generator has its AVR in service it is a? correct answer: Dynamic source of reactive power 
 
Black start resource testing is done every? correct answer: 3 years 
 
Each BA shall operate its AGC on? correct answer: Tie line Frequency Bias 
 
When is voltage reduction reportable? correct answer...
-
NERC Flashcards| 97 QUESTIONS| WITH COMPLETE SOLUTIONS
- Exam (elaborations) • 5 pages • 2022
-
Available in package deal
-
- $5.49
- + learn more
EDE - Energy Deficient Entity 
 
Ime - meter error 
 
DCS - Disturbance Control Standard 
 
DFRs - Digital Fault Recorder 
 
LOFT - Linear on the fly testing 
 
SCADA - Supervisory Control and Data Acquisition 
 
EMS - Emergency Management System 
 
SPS - Special Protection Systems 
 
ACE - Area Control Error 
 
Fs - frequency Schedule 
 
RCIS - Reliability Coordinator Information System 
 
IDC - Interchange Distribution Calculator 
 
PSE - Purchasing Selling Entity 
 
NOAA - National Oceanic At...
-
NERC-CIP v5 Standards
- Exam (elaborations) • 3 pages • 2022
-
Available in package deal
-
- $4.49
- + learn more
CIP-002 correct answer: BES Cyber System Categorization 
 
CIP-003 correct answer: Security Management Controls 
 
CIP-004 correct answer: Personnel and Training 
 
CIP-005 correct answer: Electronic Security Perimeter 
 
CIP-006 correct answer: Physical Security of BES Cyber Systems 
 
CIP-007 correct answer: System Security Management 
 
CIP-008 correct answer: Incident Reporting and Response Planning 
 
CIP-009 correct answer: Recovery Plan for BES Cyber Systems 
 
CIP-010 correct ans...
-
Nerc Test| 88 QUESTIONS| WITH COMPLETE SOLUTIONS
- Exam (elaborations) • 6 pages • 2022
-
Available in package deal
-
- $8.49
- + learn more
According to Nerc Standards, an emergency interchange transaction can be exempt from tagging if it is less than_________________ correct answer: 60 minutes 
 
A BA or LSE that requests an EEA 3 must complete and EEA 3 report and submit it to the RC within how many days correct answer: 2 business days 
 
During restoration efforts load pick-ups should not exceed_____________ percentage of synchronized generation capacity correct answer: 5% 
 
What are the two components that a system operator ...
-
NERC TOP System Operations| 74 QUESTIONS| WITH COMPLETE SOLUTIONS
- Exam (elaborations) • 14 pages • 2022
-
Available in package deal
-
- $10.49
- + learn more
At what torque angle of operation does power typically begin to flow from the generator to the system? 
 
A) 90 degrees 
B) 60 degrees 
C) 30 degrees 
D) 10 degrees correct answer: 10 degrees 
 
Choose the answer that best describes the operation of a rotor. 
 
A) The stationary part of the transmission system. 
B) A type of superconductor. 
C) The stationary element of a generator that has its windings connected to the system. 
D) The excited (energized) field winding that rotates inside the...
Want to regain your expenses?
-
My NERC TEST 1| 125 QUESTIONS| WITH COMPLETE SOLUTIONS
- Exam (elaborations) • 13 pages • 2022
-
Available in package deal
-
- $10.49
- + learn more
A misoperation occurred when an overhead ground wire on a 230KV transmission line between two substations broke and fell across A phase of the line. One of the line circuit breakers failed to open causing the breaker failure relay to pick up and as a result tripped the entire substation bus off line that the failed circuit breaker was feeding off of. Who is charged with the responsibility to develop procedures to ensure misoperations are reviewed and analyzed to determine proper mitigation plans...
-
NERC Pre test| 83 QUESTIONS| WITH COMPLETE SOLUTIONS
- Exam (elaborations) • 6 pages • 2022
-
Available in package deal
-
- $8.49
- + learn more
component of an electrical power system that can function as a motor or as a VAR generator is called a: correct answer: Synchronous condenser 
 
What are examples of measuring devices in system protection? correct answer: Current transformers, potential transformers, coupling capacitance voltage transformers. 
 
If the load on a three phase system is balanced equally among the phases, how much current will flow on the neutral point? correct answer: neutral current will be zero 
 
What are the...
-
NERC SOS quiz| 326 questions| WITH COMPLETE SOLUTIONS
- Exam (elaborations) • 32 pages • 2022
-
Available in package deal
-
- $12.49
- + learn more
If a Balancing Authority does not comply with the Control Performance Standard, the Balancing Authority is not permitted to provide which of the following for any other Balancing Authority entities? correct answer: Regulation of other services related to control performance 
 
1. It is the obligation of each Balancing Authority to fulfill its commitment to the Interconnection and not ________ the other balancing Authorities in the Interconnection correct answer: Burden 
 
A Balancing Authority...
-
NERC Test | 222 Questions| WITH COMPLETE SOLUTIONS
- Exam (elaborations) • 16 pages • 2022
-
Available in package deal
-
- $12.49
- + learn more
What percentage of load gives a 1 Hz change in an island condition? correct answer: 6-10% (Think 6-10 day island vacation) 
 
If ACE is Zero but system Hz is off, what should a system operator do? correct answer: Nothing! ACE bias and interchange schedule will improve frequency 
 
If ACE is Zero, why not adjust generation to help frequency? correct answer: Could overload equipment, this is a NERC violation 
 
When restoring from blackout condition, what should be done with load? correct answe...
-
Final Assessment Correct answers| NERC EXAM| 317 QUESTIONS| 52 PAGES (WITH COMPLETE SOLUTIONS)
- Exam (elaborations) • 52 pages • 2022
-
Available in package deal
-
- $12.49
- 1x sold
- + learn more
When using a dynamic schedule and the energy profile in an hour is >250 MW and the actual hourly integration deviates from the hourly energy profile by ____ the tag must be modified. 
A. 100 MW 
B. 10% 
C. 50 MW 
D. 25% correct answer: B. 10% 
 
Dry steam plants, flash steam plants, and binary cycle power plants are the three main types of what kind of generating plant? 
A. Nuclear generators 
B. Combustion turbine generators 
C. Geothermal generators 
D. Hydroelectric generators correct ans...
How much did you already spend on Stuvia? Imagine there are plenty more of you out there paying for study notes, but this time YOU are the seller. Ka-ching! Discover all about earning on Stuvia