Week 3 Homework: AIB Problems questions with correct answers
- Exam (elaborations) • 4 pages • 2021
-
- $13.49
- + learn more
Problem 1 
 
The following data were obtained from a project to create a new portable electronic. 
 
Activity	Duration	Predecessors	 
A		5 Days		--- 
B		6 Days		--- 
C		8 Days		--- 
D		4 Days		 
E		3 Days		 
F		5 Days		 
G		5 Days		 
H		9 Days		 
I		12 Days	 
 
Step 1: Construct a network diagram for the project. 
Step 2: Answer the following questions: (15 points total) 
 
a)	What is the Scheduled Completion of the Project? (5 points) 
 
 
b)	What is the Critical Path of the Project? (5 points)...
-
PROJ586_W3_Homework_AIB_Problems
- Exam (elaborations) • 5 pages • 2021
-
- $15.99
- + learn more
PROJ586_W3_Homework_AIB_Problems 
 
Problem 1 
 
The following data were obtained from a project to create a new portable electronic. 
 
Activity	Duration	Predecessors	 
A		5 Days		--- 
B		6 Days		--- 
C		8 Days		--- 
D		4 Days		A, B 
E		3 Days		C 
F		5 Days		D 
G		5 Days		E, F 
H		9 Days		D 
I		12 Days	G 
 
Step 1: Construct a network diagram for the project. 
Step 2: Answer the following questions: (15 points total) 
 
a)	What is the Scheduled Completion of the Project? (5 points) 
 
 
b)	What...