PROJ586_W3_Homework_AIB_Problems
- Institution
- Devry University
PROJ586_W3_Homework_AIB_Problems Problem 1 The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A, B E 3 Days C F 5 Days D G 5 Days E, F H 9 Days D I 12...