WGU C176 CompTIA Project+ questions with correct answers
- Exam (elaborations) • 21 pages • 2024
- Available in package deal
-
- $14.49
- + learn more
Three-point estimate Correct Answer-(most likely estimate + optimistic estimate + pessimistic estimate)/3 = (40 + 24 + 65)/3 = 43 hours 
 
formula for SV (schedule variance) Correct Answer-SV = EV - PV 
 
project scope documents Correct Answer-product description, key deliverables, success and acceptance criteria, key performance indicators, exclusions, assumptions, and constraints 
 
scope statement Correct Answer-The scope statement is used as a baseline for future project decisions. The scope...
-
WGU C176 CompTIA Project (business of IT project management) 2024 course requirement
- Exam (elaborations) • 22 pages • 2024
-
Available in package deal
-
- $11.99
- + learn more
WGU C176 CompTIA Project (business of IT project management) 2024 course requirement
-
WGU C176 CompTIA Project + Terms Complete Questions And Answers
- Exam (elaborations) • 17 pages • 2023
-
Available in package deal
-
- $12.99
- + learn more
WGU C176 CompTIA Project + Terms Complete Questions And Answers 
WGU C176 CompTIA Project + Terms Complete Questions And Answers 
WGU C176 CompTIA Project + Terms Complete Questions And Answers
-
WGU C176 CompTIA Project+ Questions And Answers With Latest Quiz
- Exam (elaborations) • 13 pages • 2023
-
Available in package deal
-
- $12.49
- + learn more
WGU C176 CompTIA Project+ Questions And Answers With Latest Quiz 
WGU C176 CompTIA Project+ Questions And Answers With Latest Quiz 
WGU C176 CompTIA Project+ Questions And Answers With Latest Quiz
-
WGU C176 Comptia Project | 140 Questions and Answers with complete solution
- Exam (elaborations) • 16 pages • 2023
-
- $8.49
- + learn more
Three-point estimate - (most likely estimate + optimistic estimate + pessimistic estimate)/3 = (40 
+ 24 + 65)/3 = 43 hours 
formula for SV (schedule variance) - SV = EV - PV 
project scope documents - product description, key deliverables, success and acceptance criteria, 
key performance indicators, exclusions, assumptions, and constraints 
scope statement - The scope statement is used as a baseline for future project decisions. The 
scope statement includes the project objectives, a project d...
Get paid weekly? You can!
-
WGU C176 Comptia Project+ Flashcards Correct 100%
- Exam (elaborations) • 13 pages • 2023
-
- $10.99
- + learn more
Three-point estimate - ANSWERS(most likely estimate + optimistic estimate + pessimistic estimate)/3 = (40 + 24 + 65)/3 = 43 hours 
 
formula for SV (schedule variance) - ANSWERSSV = EV - PV 
 
project scope documents - ANSWERSproduct description, key deliverables, success and acceptance criteria, key performance indicators, exclusions, assumptions, and constraints 
 
scope statement - ANSWERSThe scope statement is used as a baseline for future project decisions. The scope statement includes the ...
-
WGU C176 Comptia Project+ Flashcards ALL SOLUTION LATEST 100% CORRECT SPRING FALL-2023/24 EDITION GUARANTEED GRADE A+
- Other • 14 pages • 2023
-
- $14.29
- + learn more
Three-point estimate 
(most likely estimate + optimistic estimate + pessimistic estimate)/3 = (40 + 24 + 65)/3 = 43 hours 
formula for SV (schedule variance) 
SV = EV - PV 
project scope documents 
product description, key deliverables, success and acceptance criteria, key performance indicators, exclusions, assumptions, and constraints 
scope statement 
The scope statement is used as a baseline for future project decisions. The scope statement includes the project objectives, a project descript...