Cosc 353 exam 2 - Study guides, Class notes & Summaries
Looking for the best study guides, study notes and summaries about Cosc 353 exam 2? On this page you'll find 14 study documents about Cosc 353 exam 2.
All 14 results
Sort by
-
COSC 353 Exam 2 - Escamilla With Complete Solution
- Exam (elaborations) • 17 pages • 2024
- Available in package deal
-
- $9.99
- + learn more
COSC 353 Exam 2 - Escamilla With Complete Solution...
-
COSC 353 Exam 2 With Complete Solution
- Exam (elaborations) • 14 pages • 2024
- Available in package deal
-
- $9.99
- + learn more
COSC 353 Exam 2 With Complete Solution...
-
COSC 353 (100% Errorless Answers)
- Package deal • 9 items • 2023
-
- $47.16
- 1x sold
- + learn more
COSC 353 - Exam 3 (100% Correct Answers)
COSC 353 Final (All Correct 100%)
COSC 353 - Exam 1 – Escamilla (with 100% Verified Answers)
COSC 353 Exam 2 (A+ Graded Already)
COSC 353 Exam 2 (All Correctly Answered)
COSC 353 Final (100% Errorless Answers)
COSC 353 – Final (100% Accurately Answered)
Construction Project Management (COSC 353) Exam 1 – Esc
-
COSC 353 Exam 2 Questions and Answers
- Exam (elaborations) • 11 pages • 2024
-
- $12.49
- + learn more
COSC 353 Exam 2 Questions and Answers 
Chapters 7,8,9,11,12,13 - Correct Answer️️ -Even though syllabus doesn't say 12 and 
13... 
To ensure max competitive advantage and the best sub price for an owner, a 
construction manager should seek 12 or more bidders per work package. T/F - Correct 
Answer️️ -False 
A bid breakdown submitted by the bidder can be useful in guiding contractor progress 
payments. T/F - Correct Answer️️ -True 
Builder's risk insurance insures the property while...
-
Cosc 353 Exam 2 Actual Exam Questions With Verified Correct Answers| Latest Update
- Exam (elaborations) • 9 pages • 2023
-
- $9.99
- + learn more
Cosc 353 Exam 2 Actual Exam 
Questions With Verified Correct Answers| 
Latest Update 
Estimate accuracy increases as what? - ANSWER the design 
becomes more precisely defined 
What do estimates not guarantee? - ANSWER Costs 
Rough order of magnitude estimates Units? Advantages? 
Accuracy? - ANSWER -Units mainly developed from past 
projects 
-ADV- Quickly calculated 
-Accuracy= +/- 20% 
Square foot and cubic foot estimates - ANSWER -Schematic 
design -15% design complete 
-Historical datab...
And that's how you make extra money
-
COSC 353 Exam 2 (A+ Graded Already)
- Exam (elaborations) • 6 pages • 2023
-
Available in package deal
-
- $10.09
- + learn more
Estimate accuracy increases as what? correct answers the design becomes more precisely defined 
 
What do estimates not guarantee? correct answers Costs 
 
Rough order of magnitude estimates Units? Advantages? Accuracy? correct answers -Units mainly developed from past projects 
-ADV- Quickly calculated 
-Accuracy= +/- 20% 
 
Square foot and cubic foot estimates correct answers -Schematic design -15% design complete 
-Historical database 
-Adv 
 
Assemblies Estimates Accuracy? Unit? System? corr...
-
COSC 353 Exam 2 (All Correctly Answered)
- Exam (elaborations) • 7 pages • 2023
-
Available in package deal
-
- $10.49
- + learn more
To ensure max competitive advantage and the best sub price for an owner, a construction manager should seek 12 or more bidders per work package. T/F correct answers False 
 
A bid breakdown submitted by the bidder can be useful in guiding contractor progress payments. T/F correct answers True 
 
Builder's risk insurance insures the property while it is under construction for damage resulting from fire, smoke, water, explosion, and vandalism. T/F correct answers True 
 
A bidder who submits the ...
-
COSC 353 Project Management Exam 2 With Complete Solution
- Exam (elaborations) • 10 pages • 2024
- Available in package deal
-
- $8.99
- + learn more
COSC 353 Project Management Exam 2 With Complete Solution...
-
COSC 353 - Exam 1 Questions With Verified Correct Answers| Latest Update
- Exam (elaborations) • 24 pages • 2023
-
- $11.99
- + learn more
COSC 353 - Exam 1 Questions With 
Verified Correct Answers| Latest 
Update 
1. Which of the following should be considered in establishing an 
organizational structure for the management of a construction project? 
A. How work functions will be compartmentalized 
B. The number of resources to be committed to the project 
C. Whether decisions should be made in a centralized or decentralized manner 
D. The degree of the need for interdisciplinary work 
E. All of the above - ANSWER E. All of the...
-
Cosc 353 Final Real Exam Questions { CH1-11} With Verified Correct Answers| Latest Update
- Exam (elaborations) • 17 pages • 2023
-
- $9.99
- + learn more
Cosc 353 Final Real Exam Questions 
With Verified Correct Answers| Latest 
Update 
Which of the following is not true about the future of the construction industry? - 
ANSWER The need for permits and regulations will decrease 
Which of the following categories of projects is often publicly funded and called 
infrastructure? - ANSWER Heavy Engineering 
The development of the printing press was a key event in the evolution of the design 
and construction industry. - ANSWER True 
Compared with...
Did you know that on average a seller on Stuvia earns $82 per month selling study resources? Hmm, hint, hint. Discover all about earning on Stuvia