Cm 4101 - Study guides, Class notes & Summaries
Looking for the best study guides, study notes and summaries about Cm 4101? On this page you'll find 17 study documents about Cm 4101.
All 17 results
Sort by
-
CM 4101 Exam 1 Questions And Answers 2024
- Exam (elaborations) • 15 pages • 2024
-
- $13.99
- + learn more
CM 4101 Exam 1 Questions And Answers 2024 
(ESi) 
(EFi) 
(LFi) 
(LSi) 
(Ti) 
(TFi) 
(FFi) - ANS-Early Activity Start 
Early Activity Finish 
Late Activity Finish 
Late Activity Start 
Duration 
Total Float 
Free Float 
Why Plan, Schedule and Control? (6) - ANS--Complexity of construction projects 
-To control resource consumption 
-To communicate the construction plan 
-To establish production goals 
-To monitor and measure project progress 
-To manage changes 
What is a primary means that gen...
-
CM 4101 Final Exam | With 100% Correct Answers, Graded A
- Exam (elaborations) • 7 pages • 2024
-
- $15.99
- + learn more
CM 4101 Final Exam | With 100% Correct Answers, Graded A During which of the following process, questions such as what activities should be scheduled are typically asked and answered? a. Planning b. Scheduling c. Control Using traditional bar charts, it is always easy to tell the logic relationships between activities. a. True b. False An event consumes a. Resources b. Time c. Both Resources and Time d. Neither resources nor time Which of the following is correct regarding CPM and PERT? a. The...
-
CM 4101 Final Exam Prep Test Questions Answered 100% Correct
- Exam (elaborations) • 22 pages • 2024
- Available in package deal
-
- $12.99
- + learn more
Bar Charts - Answer simple and time scaled presentations that show how major work 
activities are scheduled 
advantages bar charts - Answer simple and easy to use 
disadvantages bar charts - Answer -cannot determine project status 
-cannot determine needs for adjustments 
-activites for acceleration cannot be determined 
-relies on extra links to show logical relationships between activities, otherwise 
relationships cannot be determined 
networks - Answer graphic representations using nodes and...
-
CM 4101 Exam Questions Solved 100% Correct
- Exam (elaborations) • 15 pages • 2024
- Available in package deal
-
- $12.74
- + learn more
What are graphic representations using nodes and links. - Answer Networks 
What is a discrete part of a project that can be identified for planning, scheduling, 
monitoring, and controlling the construction project. - Answer Activity 
What is the point in time or an instant at which the status of completion of a project or 
an activity can be defined. - Answer Even
-
CM 4101 final Exam Questions Solved 100% Correct
- Exam (elaborations) • 14 pages • 2024
- Available in package deal
-
- $12.99
- + learn more
work breakdown structure - Answer a _______ provides a framework for breaking a 
project down into successively greater detail by level and organizing activities that make 
up a project 
sequencing, scheduling - Answer a WBS organizes the work of a project but does not 
address the _____ and the _____ of project activities
Make study stress less painful
-
Study set for CM 4101 Final Exam Review Questions and Answers 2024/2025
- Exam (elaborations) • 8 pages • 2024
-
- $13.49
- + learn more
Study set for CM 4101 Final Exam 
Review Questions and Answers 
2024/2025 
Construction Planning - CORRECT ANSWER-The process of determining how a project will be carried out. Planning answers questions: who? what? where?, and how? 
Construction Scheduling - CORRECT ANSWER-Process to determine when activities need to be started and completed. Answers the question: when? 
Project Control - CORRECT ANSWER-Is an active process to monitor and update the construction plan and the schedule. 
Monitorin...
-
CM 4101 final Exam Questions Solved 100% Correct
- Exam (elaborations) • 13 pages • 2024
- Available in package deal
-
- $12.99
- + learn more
What is not true about classic bar charts? 
a. Bar charts use a time-scaled presentation 
b. Bar charts often directly show resource consumption of each activity 
c. Bar charts can show the relative of each activity 
d. Bar charts cannot show the actual status of a project - Answer b. Bar charts often 
directly show resource consumption of each activity 
c. Bar charts can show the relative of each activity
-
CM 4101 Exam Questions Answered 100% Correct
- Exam (elaborations) • 9 pages • 2024
- Available in package deal
-
- $12.49
- + learn more
Work breakdown structure - Answer provides a framework for breaking a project down 
into successively greater detail by level and organizing activities that make up a project. 
wbs - Answer A ____ organizes the work of a project but does not address the 
sequencing and the scheduling of project activities. 
milestones - Answer are included in schedules to mark a particular point in time for 
reference or measurement
-
CM 4101 EXAMS BUNDLE WITH Questions Solved 100% Correct
- Package deal • 9 items • 2024
-
- $33.49
- + learn more
CM 4101 EXAMS BUNDLE WITH Questions Solved 100% Correct
-
CM 4101 Exam Prep Questions Answered 100% Correc
- Exam (elaborations) • 5 pages • 2024
- Available in package deal
-
- $11.99
- + learn more
A significant difference between "planning" and "scheduling" is, - Answer Scheduling 
determines when to do, and planning determines what to do, how to and by whom. 
What is NOT true about an activity? - Answer An activity usually does not need to be 
measurable 
There is an activity, installing exterior sheathing. A crew can install 1,200 sf per day, and 
the total quantity is 3,200 SF. What is the duration of this activity? - Answer 3 days
Study stress? For sellers on Stuvia, these are actually golden times. KA-CHING! Earn from your study resources too and start uploading now. Discover all about earning on Stuvia