Rmc pmp - Study guides, Class notes & Summaries

Looking for the best study guides, study notes and summaries about Rmc pmp? On this page you'll find 54 study documents about Rmc pmp.

Page 3 out of 54 results

Sort by

PMP-RMC EMV Questions and answers
  • PMP-RMC EMV Questions and answers

  • Exam (elaborations) • 8 pages • 2023
  • Available in package deal
  • PMP-RMC EMV Questions and answers
    (0)
  • $15.99
  • + learn more
PMP-RMC Super Exam-2 Failed questions with 100% correct answers
  • PMP-RMC Super Exam-2 Failed questions with 100% correct answers

  • Exam (elaborations) • 47 pages • 2023
  • (1)* Question ID: 200 Your project team has identified dependencies on six related projects that are providing major deliverables to your project. Some of these projects have a very similar scope and may overlap with your deliverables. In light of this, which of the following processes should you be most concerned about? A. Validate Scope B. Plan Risk Responses C. Plan Communications Management D. Control Scope The correct answer is B. The biggest concern must be the risks other proje...
    (0)
  • $16.49
  • + learn more
PMP-RMC Super Exam-3 Failed questions and answers
  • PMP-RMC Super Exam-3 Failed questions and answers

  • Exam (elaborations) • 11 pages • 2023
  • (33)* Question ID: 483 As per the chart, the team member completing activity E is not performing very well. After much argument, the functional manager agrees to assign a different person to activity E, but this will increase activity E's duration to seven months. What is the effect of this change? A. The project will be delayed because activity E is on the critical path. B. None, because activity E is not on the critical path. C. None, because activity E has float of four. D. The projec...
    (0)
  • $14.99
  • + learn more
PMP-RMC Super Exam-2 Failed questions and answers
  • PMP-RMC Super Exam-2 Failed questions and answers

  • Exam (elaborations) • 47 pages • 2023
  • (1)* Question ID: 200 Your project team has identified dependencies on six related projects that are providing major deliverables to your project. Some of these projects have a very similar scope and may overlap with your deliverables. In light of this, which of the following processes should you be most concerned about? A. Validate Scope B. Plan Risk Responses C. Plan Communications Management D. Control Scope The correct answer is B. The biggest concern must be the risks other proje...
    (0)
  • $14.49
  • + learn more
PMP-RMC EMV Questions and answers.
  • PMP-RMC EMV Questions and answers.

  • Exam (elaborations) • 8 pages • 2023
  • (1) Question ID: 1026 If a project has a 60 percent chance of a US $100,000 profit and a 40 percent chance of a US $100,000 loss, the expected monetary value (EMV) for the project is: A. $20,000 profit B. $60,000 loss C. $40,000 loss D. $100,000 profit The correct answer is A. Expected monetary value is calculated by EMV = probability × impact. We need to calculate both positive and negative values and then add them. 0.6 × $100,000 = $60,000 0.4 × ($100,000) = ($40,000) Expected...
    (0)
  • $14.49
  • + learn more
PMP-RMC EMV Questions and answers already graded A+
  • PMP-RMC EMV Questions and answers already graded A+

  • Exam (elaborations) • 9 pages • 2023
  • (1) Question ID: 1026 If a project has a 60 percent chance of a US $100,000 profit and a 40 percent chance of a US $100,000 loss, the expected monetary value (EMV) for the project is: A. $20,000 profit B. $60,000 loss C. $40,000 loss D. $100,000 profit The correct answer is A. Expected monetary value is calculated by EMV = probability × impact. We need to calculate both positive and negative values and then add them. 0.6 × $100,000 = $60,000 0.4 × ($100,000) = ($40,000) Expected...
    (0)
  • $14.99
  • + learn more
PMP Prep (RMC 8th Ed.) - Complete PM Process with 100% correct answersPMP Prep (RMC 8th Ed.) with 100% correct answers
  • PMP Prep (RMC 8th Ed.) - Complete PM Process with 100% correct answersPMP Prep (RMC 8th Ed.) with 100% correct answers

  • Exam (elaborations) • 8 pages • 2023
  • Select PM Initiating1 Determine company culture and existing systems Initiating2 Collect processes, procedures, and historical information Initiating3 Divide large projects into phases Initiating4 Understand the business case Initiating5 Uncover initial requirements, assumptions, risks, constraints, and existing agreements Initiating6 Assess project and product feasibility within the given contsraints Initiating7 Create measurable objects ...
    (0)
  • $15.49
  • + learn more
PMP-RMC Super Exam-3 Failed questions with complete solutions.
  • PMP-RMC Super Exam-3 Failed questions with complete solutions.

  • Exam (elaborations) • 11 pages • 2023
  • (33)* Question ID: 483 As per the chart, the team member completing activity E is not performing very well. After much argument, the functional manager agrees to assign a different person to activity E, but this will increase activity E's duration to seven months. What is the effect of this change? A. The project will be delayed because activity E is on the critical path. B. None, because activity E is not on the critical path. C. None, because activity E has float of four. D. The projec...
    (0)
  • $14.99
  • + learn more
PMP RMC HT book 9th Project Management Framework
  • PMP RMC HT book 9th Project Management Framework

  • Exam (elaborations) • 5 pages • 2023
  • What is the definition of a project? Temporary endeavor—with a beginning and an end Creates a unique product, service, or result What is operational work? Ongoing work to support the business and systems of the organization What is the definition of a program? What is the definition of a portfolio? Program: A group of related projects, managed in a coordinated way Portfolio: A group of programs, individual projects, and other related operational work that are prioritized and...
    (0)
  • $14.99
  • + learn more