If load is undetermined who is to find out if load weight does not exceed crane rating at radius 
at which the load is to be lifted - ANSWER Person responsible for lift 
Where should climbing instructions be kept - ANSWER ON Site 
All climbing operations shall be performed under the supervision of - ANSWER Qualified 
person 
When cranes are erected, load limiting devices shall be tested for proper setting and 
operation - ANSWER Before crane is placed in service 
Hooks shall be equipped with lat...
-
NCCCO MOBILE CRANE EXAM QUESTIONS AND ANSWERS
- Exam (elaborations) • 11 pages • 2024
- Available in package deal
-
- $11.49
- + learn more
NCCCO MOBILE CRANE EXAM QUESTIONS AND ANSWERS 
 
 
1. What action does a signal person intend the operator to perform if he extends his arm at shoulder height, makes a fist with his hand, and sticks his/her thumb up? 
a. Boom down 
b. Swing 
c. Boom up 
d. Extend boom - ANS c. 
 
2. When hoisting personnel, within what percentage of level must a telescopic boom crane be in order for the gross ratings in the load chart to remain valid? 
a. 1% 
b. 2% 
c. 5% 
d. 8% - ANS a. 
 
3. The lo...
-
OECP Exam Questions With 100% Correct Answers 2024/2025 (GRADED)
- Exam (elaborations) • 23 pages • 2024
-
- $15.99
- + learn more
OECP Exam Questions With 100% Correct Answers 2024/2025 (GRADED) The shaded area on a load chart 
indicates _______? 
A structural chart 
3. The minimum distance to a power 
line of unknown voltage is ? 
50' 
4. When hoisting personnel and have 
known voltage, can you use Table A 
and get closer than 20'? 
Never! 
5. What is the minimum tale swing 
clearance requirement 
2' 
6. What kind of rigger is required for 
A/D? 
Qualified Rigger 
7. Signal training is now required in 
the construction...
-
NCCCO Core Questions and Answers with Complete Solutions Graded A 2024
- Exam (elaborations) • 22 pages • 2024
-
Available in package deal
-
- $12.49
- + learn more
The term "Superstructure or Upper works" refers to the area of the crane: 
Above the swing circle 
 
 
A crane must be level within _______% for the load chart ratings to be valid? 
1% 
 
 
On what principle is crane stability based? 
Leverage 
 
 
What would be the effect of moving the tipping axis closer to the cranes center of gravity? 
Reduced stability 
 
 
Which of the following matches the appropriate load chart to a particular crane? 
Serial number 
 
 
A durable rating chart with legi...
-
NCCCO Tower Crane Exam Questions and Answers Latest Update 2024/2025 (100% Correct)
- Exam (elaborations) • 16 pages • 2024
- Available in package deal
-
- $13.99
- + learn more
NCCCO Tower Crane Exam Questions and Answers Latest Update 2024/2025 (100% Correct) Splices in rall tracks shall have - ANSWER Smooth Joints 
Hydraulic systems should have their proper fluid level checked - ANSWER Daily 
If power fails during operations, the following shouldn't apply - ANSWER Do your best to 
finish moving load where it was designated to go 
If load is undetermined who is to find out if load weight does not exceed crane rating at radius 
at which the load is to be lifted - ANSW...
Want to regain your expenses?
-
1B Hoisting Prep Questions and Answers Already Passed
- Exam (elaborations) • 16 pages • 2024
- Available in package deal
-
- $9.99
- + learn more
1B Hoisting Prep Questions and 
Answers Already Passed 
 
all hoisting machinery shall be operated in accordance with the: manufacturer's specification 
 
maintenance repair and refueling shall be done when the machine is: inoperable and secure 
 
visual inspection shall be made ___________ of wire ropes, bearings, gears, friction clutches, 
brakes, chain drives and other parts subject to wear on all hoisting machinery to ensure against 
development of unsafe conditions daily 
 
factory of safe...
-
NCCCO MOBILE CRANE EXAM QUESTIONS AND ANSWERS LATEST UPDATE 2024/2025 (100% CORRECT)
- Exam (elaborations) • 12 pages • 2024
-
Available in package deal
-
- $14.49
- + learn more
NCCCO MOBILE CRANE EXAM QUESTIONS AND ANSWERS LATEST 2024/2025 (100% CORRECT) When hoisting personnel, within what percentage of level must a telescopic boom crane be in 
order for the gross ratings in the load chart to remain valid? 
a. 1% 
b. 2% 
c. 5% 
d. 8% correct answers a. 
3. The load line of the crane you're operating contacts an energized power line. There's no sign of 
any other danger, such as fire. What should you do? 
a. Climb down carefully from the crane cab 
b. Jump down, feet...
-
Mobile Cranes 3 Questions & Answers | 100% Correct Answers | Verified | Latest 2024 Version
- Exam (elaborations) • 11 pages • 2024
- Available in package deal
-
- $10.49
- + learn more
All slings for rigging they must have? - Sling identification 
While performing a shift inspection which one of these are required to be inspected as per OSHA 
1926.1412 - Pins, bearings, and locking devices for significant wear. 
What is the signal person directing the crane operator to do? (Picture of man holding his arm straight 
out to his side, parallel to ground with his palm facing down). - Stop 
What does 4 x 12,920 equal? (no calculator) - 51,680 
What is the signal person directing the...
-
OSHA 500 Construction Trainer Questions with Correct Answers
- Exam (elaborations) • 17 pages • 2023
-
- $12.99
- + learn more
OSHA 500 Construction Trainer Questions with Correct Answers 
3 major types of rigging hazards - Correct Answer falls 
struck by 
electric 
 
materials handling aparatus in rigging (3) - Correct Answer wire ropes 
chains 
synthetic (web) slings 
 
inspections (how often and by whom) - Correct Answer prior to each use by a competent person 
 
rigging restrictions for wire rope - Correct Answer less than 10% broken wires in 8 diameter 
 
requirements for special custom-designed accessories in rela...
-
NCCCO MOBILE CRANE EXAM – 99 QUESTIONS WITH 100% CORRECT ANSWERS
- Exam (elaborations) • 17 pages • 2023
- Available in package deal
-
- $15.99
- + learn more
1. What action does a signal person intend the operator to perform if he extends his arm at shoulder height, makes a fist with his hand, and sticks his/her thumb up? 
a. Boom down 
b. Swing 
c. Boom up 
d. Extend boom 
c. 
 
 
 
2. When hoisting personnel, within what percentage of level must a telescopic boom crane be in order for the gross ratings in the load chart to remain valid? 
a. 1% 
b. 2% 
c. 5% 
d. 8% 
a. 
 
 
 
3. The load line of the crane you're operating contacts an energized powe...