CM 4101 Midterm Exam Questions Solved 100% Correct
- Exam (elaborations) • 4 pages • 2024
- Available in package deal
-
- $11.49
- + learn more
what is not true about an event - Answer an event usually consumes resources. 
an event usually takes time. 
major types of activities - Answer procurement, production/construction, 
management 
The conditions of limited resource availability dictate certain activities cannot be 
performed simultaneously. This is: - Answer resource constraint
-
CM 4101 Exam Prep Test Questions Answered 100% Correct
- Exam (elaborations) • 4 pages • 2024
- Available in package deal
-
- $11.49
- + learn more
Starting a new project in P6 you must first: - Answer File - Close All 
3 Establishing Relationships - Answer Finish-to-start, Start-to-start, Finish-to-finish 
Finish-to-start (FS) - DEFAULT - Answer A finishes, B can start 
Start-to-start (SS) - Answer A starts, B can start
-
Study set for CM 4101 Final Exam Review Questions and Answers 2024/2025
- Exam (elaborations) • 8 pages • 2024
- Available in package deal
-
- $13.49
- + learn more
Study set for CM 4101 Final Exam 
Review Questions and Answers 
2024/2025 
Construction Planning - CORRECT ANSWER-The process of determining how a project will be carried out. Planning answers questions: who? what? where?, and how? 
Construction Scheduling - CORRECT ANSWER-Process to determine when activities need to be started and completed. Answers the question: when? 
Project Control - CORRECT ANSWER-Is an active process to monitor and update the construction plan and the schedule. 
Monitorin...
-
CM 4101 FINAL EXAM WITH GUARANTEED ACCURATE ANSWERS
- Exam (elaborations) • 12 pages • 2024
-
- $11.99
- + learn more
Notice to proceed - Accurate Answersthe document that typically marks the actual beginning of construction duration 
 
liquidated damages - Accurate Answersprovisions in a contract such as "damages for avoidable delay 5000 per day" 
 
yes - Accurate Answerscan resource allocation cause changes to activities dependencies? 
 
no - Accurate Answerscan the duration of a project be changed after resource leveling? 
 
S-curve - Accurate Answersin cash flow analysis, used to represent cumulative sum ...
-
CM 4100 Assignments Questions Solved 100% Correct
- Exam (elaborations) • 12 pages • 2024
- Available in package deal
-
- $12.74
- + learn more
The conditions of limited resource availability dictate certain activities cannot be 
performed simultaneously. This is, 
Select one: 
a. Physical constraints 
b. Resource constraints 
c. Safety constraints 
d. Contractual constraints - Answer Resource constraints
Want to regain your expenses?
-
Package deal for Final Exam Guide for CM 4100 Exam 1 Questions and Verified Solutions
- Package deal • 7 items • 2024
-
- $40.56
- + learn more
Final Exam Guide for CM 4100 Exam 1 Questions and Verified Solutions
CMGT 4100 Final Exam Questions and Answers 100% Verified
Study set for CM 4101 Final Exam Review Questions and Answers 2024/2025
CM 4100 Assignments with Questions and Answers 100% Correct
cM 4100 Module 1-6 Quizzes and Answers 100% Correct
practice Exam for CEE 4100 Test 2 Questi
-
CM 1401 (Languages) Final Exam Questions and Accurate Answers Rated A.
- Exam (elaborations) • 32 pages • 2024
-
- $16.39
- + learn more
CM 1401 (Languages) Final Exam 
Questions and Accurate Answers Rated 
A.
How much did you already spend on Stuvia? Imagine there are plenty more of you out there paying for study notes, but this time YOU are the seller. Ka-ching! Discover all about earning on Stuvia