UNL's new College of Engineering Building (Kiewit Hall) uses which of the following project delivery methods? a. CMar b. design/build c. IPD d. P3 e. Design-Bid-Build correct answers a. CMar It is usually easy for a general contractor to obtain private bid opportunities than it is to obta...

[Montrer plus]

Aperçu 2 sur 15  pages

  • 4 août 2024
  • 15
  • 2024/2025
  • Examen
  • Questions et réponses
  • CNST 379
  • CNST 379
avatar-seller
Exam 1- CNST 379 || All Questions Answered Correctly.
UNL's new College of Engineering Building (Kiewit Hall) uses which of the following project
delivery methods?

a. CMar
b. design/build
c. IPD
d. P3
e. Design-Bid-Build correct answers a. CMar

It is usually easy for a general contractor to obtain private bid opportunities than it is to obtain
public bid opportunities.

True or False correct answers false

An RFP, will typically contain which of the following: (Select all that apply)
-Type of owner contract to be used
-Anticipated cost and desired schedule
-Time and date of bid response
-Owner's contact information
-Type of project delivery method correct answers all the above

The RFQ process, if utilized by and owner, is typically done in advance of the RFP process.(T/F)
correct answers True

Which of the follow could be considered public owners? (Select all that apply.) correct answers -
Lincoln Public Schools
-University of Nebraska - Lincoln
-Colorado Department of Transportation

A public owner can award a project to which ever firm they see fit. (T/F) correct answers false

RFP stands for request for ______________. (one word, lowercase, singular) correct answers
Proposal

Which project delivery method typically results with the least risk to the GC or Construction
Manager?
a. public Private Partnership(P3)
b. CM at Risk
c. CM not at risk
d. Design- Bid- Build
e. Design/ Build
f. IPD correct answers CM not at risk

, Which project delivery method does the architect and engineer contract directly with the general
contractor/Construction Manager?
a.Design-Bid-Build
b.CM at Risk
c. Design/Build
d.CM not at Risk
e. IPD correct answers design/ Build

Which project delivery method typically results in the owner receiving the lowest possible
project cost?
a. Integrated Project Delivery (IPD)
b.CM not at Risk
c. CM at Risk
d. Design/Build
e. Design-Bid-Build correct answers design-Bid-Build

Which project delivery methods (choose all that apply) does the general contractor/construction
manager enter into a contractual agreement with the owner BEFORE the final contract amount
has been determined?
a. IPD
b. CM at Risk
c. CM not at risk
d. design/Build
c. Design-bid- build correct answers IPD, CMar, CMR, design/build

The term "Hard Bid" is generally associated with which Project Delivery Method?
- Cmar
-design/build
-design-bid-build
-ipd
-p3 correct answers Design-bid-build

Lump sum contracts are typically used with the design-bid- build project delivery method( T/F)
correct answers true

A contractor enters into a cost plus contract with a GMP for the construction of a new hotel. The
contractor's final costs exceeds the GMP. In this instance the owner will be responsible for
reimbursing the contractor for their costs incurred that were above the GMP. (T/F) correct
answers false

GMP stands for guaranteed __________________ price. correct answers Maximum

In a unit and unit price contract, the general contractor tasks the risk on ensuring the project
quantities are accurate. correct answers false

Les avantages d'acheter des résumés chez Stuvia:

Qualité garantie par les avis des clients

Qualité garantie par les avis des clients

Les clients de Stuvia ont évalués plus de 700 000 résumés. C'est comme ça que vous savez que vous achetez les meilleurs documents.

L’achat facile et rapide

L’achat facile et rapide

Vous pouvez payer rapidement avec iDeal, carte de crédit ou Stuvia-crédit pour les résumés. Il n'y a pas d'adhésion nécessaire.

Focus sur l’essentiel

Focus sur l’essentiel

Vos camarades écrivent eux-mêmes les notes d’étude, c’est pourquoi les documents sont toujours fiables et à jour. Cela garantit que vous arrivez rapidement au coeur du matériel.

Foire aux questions

Qu'est-ce que j'obtiens en achetant ce document ?

Vous obtenez un PDF, disponible immédiatement après votre achat. Le document acheté est accessible à tout moment, n'importe où et indéfiniment via votre profil.

Garantie de remboursement : comment ça marche ?

Notre garantie de satisfaction garantit que vous trouverez toujours un document d'étude qui vous convient. Vous remplissez un formulaire et notre équipe du service client s'occupe du reste.

Auprès de qui est-ce que j'achète ce résumé ?

Stuvia est une place de marché. Alors, vous n'achetez donc pas ce document chez nous, mais auprès du vendeur FullyFocus. Stuvia facilite les paiements au vendeur.

Est-ce que j'aurai un abonnement?

Non, vous n'achetez ce résumé que pour €11,73. Vous n'êtes lié à rien après votre achat.

Peut-on faire confiance à Stuvia ?

4.6 étoiles sur Google & Trustpilot (+1000 avis)

77858 résumés ont été vendus ces 30 derniers jours

Fondée en 2010, la référence pour acheter des résumés depuis déjà 14 ans

Commencez à vendre!
€11,73
  • (0)
  Ajouter