Bsci 4610 - Study guides, Class notes & Summaries
Looking for the best study guides, study notes and summaries about Bsci 4610? On this page you'll find 8 study documents about Bsci 4610.
All 8 results
Sort by
-
BSCI 4610 Question and answers 100% correct 2024
- Exam (elaborations) • 17 pages • 2024
- Available in package deal
-
- $13.99
- + learn more
BSCI 4610 Question and answers 100% correct 2024 BSCI 4610 — Scheduling Quiz 2, Wetzel 
 
FS Relationship 
What is the following Precedence Diagram an example of 
 
 
Concurrent Activities 
What is the following Precedence Diagram an example of? 
 
 
Multiple Concurrent Activities 
What is the following Precedence Diagram an example of? 
 
 
Substantial Completion 
What is the following Precendence Diagram an example of? 
 
 
Top left: ES 
Top Middle: Dur 
Top Right: EF 
Middle Left: Activity...
-
BSCI 4610 Test 1 Questions with complete solution 2024
- Exam (elaborations) • 8 pages • 2024
- Available in package deal
-
- $13.99
- + learn more
BSCI 4610 Test 1 Questions with complete solution 2024 BSCI 4610 Test 1 - Scheduling 
 
Planning 
Scheduling 
Executing - correct answer What are the overall goals of a typical construction Project? 
 
Difference between planning and scheduling - correct answer -Planning Identifies activities 
-Scheduling determines logic and duration for those activities 
 
Reasons to Schedule - correct answer Coordinate and Communicate Expectations 
Incorporate Key Procurement Issues 
Track Progress...
-
BSCI 4610 Question and answers already passed 2024
- Exam (elaborations) • 7 pages • 2024
-
- $13.49
- + learn more
BSCI 4610 Question and answers already passed 2024 BSCI 4610- Quiz 3 
 
What is a Cost Loaded Schedule (CLS)? 
each applicable activity in the schedule has a dollar amount; and the sum of these activities should be equal to the total contract value 
 
 
Direct Expense 
can be billed directly to the owner as line items in a cost-loaded schedule (CLS) 
 
 
Indirect Expenses 
billable to the project, but aren't in the CLS 
 
 
How are indirect expenses billed? 
through a multiplier 
 
 
T/F: If t...
-
BSCI 4610 Test 2 Question and answers rated A+ 2024
- Exam (elaborations) • 5 pages • 2024
- Available in package deal
-
- $12.49
- + learn more
BSCI 4610 Test 2 Question and answers rated A+ 2024 BSCI 4610 Test 2 
 
owners 
A compensable delay is a failure of the ______ obligation 
 
 
a project incurs negative float due to non-excusable delays 
A Recovery Schedule is often required when... 
 
 
shared between the Contractor AND Owner 
If a contract states that time extensions will only be granted for delays to the critical path, the Contractor can assume that the float of a project is... 
 
 
Time Impact Analysis with Scheduling _____...
-
BSCI 4610 Test 1 Question and answers 100% correct 2024
- Exam (elaborations) • 5 pages • 2024
- Available in package deal
-
- $13.49
- + learn more
BSCI 4610 Test 1 Question and answers 100% correct 2024 BSCI 4610 Test 1 - Holley 
 
Hoisting and access are considered top considerations in site utilities. - correct answer T 
 
Sites with sand while easy to move, pose security issues - correct answer T 
 
Temp. underpinning insulations are considered real schedules activities with real potential to impact the schedule. - correct answer T 
 
A dewatering systems with multiple pvc pipes are installed in a sleeve around a project perimete...
Make study stress less painful
-
BSCI 4610 Quiz 2 Question and answers rated A+ 2024
- Exam (elaborations) • 4 pages • 2024
- Available in package deal
-
- $13.99
- + learn more
BSCI 4610 Quiz 2 Question and answers rated A+ 2024 BSCI 4610 Quiz 2/Test 1 
 
Project Resources - correct answer Manpower 
Material 
Machinery 
Money 
 
Biggest Concerns Regarding Material - correct answer Procurement, Storage, Lead Times 
 
Resources: Crew Productivity - correct answer High = 1.2 
Standard = 1.0 
Below = .85 
 
Ex Crew Productivity - correct answer A Standard Crew 145 yds of 6" concrete. 6,000 cyds on the project. How many days? 
 
- 6,000/145(1.0) = 41.4 Days 
 
Hig...
-
PACKAGE DEAL OF BSCI 4610 QUESTION AND ANSWERS RATED A+ 2024
- Package deal • 3 items • 2024
-
- $30.99
- + learn more
xam (elaborations)
BSCI 4610 Question and answers already passed 2024


Exam (elaborations)
BSCI 4610 Question and answers 100% correct 2024


Exam (elaborations)
BSCI 4610 Test 2 Question and answers rated A+ 2024


Exam (elaborations)
BSCI 4610 Test 1 Questions with complete solution 2024
-
BSCI 4610 Test 1 - Scheduling Questions & Answers
- Exam (elaborations) • 4 pages • 2024
-
- $10.49
- + learn more
BSCI 4610 Test 1 - Scheduling 
 
Planning 
Scheduling 
Executing - Answer- What are the overall goals of a typical construction Project? 
 
Difference between planning and scheduling - Answer- -Planning Identifies activities 
-Scheduling determines logic and duration for those activities 
 
Reasons to Schedule - Answer- Coordinate and Communicate Expectations 
Incorporate Key Procurement Issues 
Track Progress 
Forecasting - Time and Labor 
Historical Data - For Current Projects/Future Proje...
Study stress? For sellers on Stuvia, these are actually golden times. KA-CHING! Earn from your study resources too and start uploading now. Discover all about earning on Stuvia