375 Milestone NEW QUESTIONS AND ANSWERS SOLUTION 2021
1
Which of the following is the main reason a project closing can be time-consuming?
•
Resolving outstanding issues
•
Releasing the team early
•
Organizing needed documentation
•
Evaluating actuals to estimates
2
...
375 Milestone 4.docx NEW QUESTIONS AND ANSWERS SOLUTION 2021 1
Which of the following is the main reason a project closing can be time-consuming?
Resolving outstanding issues
Releasing the team early
Organizing needed documentation
Evaluating actuals to estimates
2
Which of the following reflects a team evaluation criterion?
Worked collectively to manage identified risks for the project
Met schedule requirements for completion of project tasks
Ensured completed deliverable was 95% defect-free
Managed conflicts between stakeholder groups interested in the project
3
Which of the following statements is true about the post-transfer follow-up process?
Following up takes place between the project manager and the project team.
Following up after the project should occur indefinitely.
Following up is done as a courtesy in order to demonstrate support.
Following up should be done in a face-to-face meeting.
4 Which of the following is the correct reason the team is released as the last step in the closing process?
You may need team members to meet with the project sponsor to gain approval.
You may need them to sign off on deliverable.
You cannot release them until they have another project assignment.
You may need team members to help in the transfer of ownership.
5
Which of the following is an example of a lesson learned that is related to resources used outside the organization?
The weekly delivery of project status reports facilitated the success of the project.
A piece of equipment on the production line broke down and caused a schedule delay.
A deliverable did not meet quality standards because it was not tested thoroughly.
One of the groups contracted for the project failed to meet production deadlines.
6
Which of following is true regarding warehousing information?
Most organizations use a paper storage system for warehousing project documents.
Most organizations have a specific file-naming convention for filing documentation.
Documents are warehoused at the end of each phase of a project.
Only the final project documents are warehoused for a project.
7
Which activity would Trina perform in Phase 3 of a project to create a plant nursery at a local hardware store?
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller smartzone. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $8.49. You're not tied to anything after your purchase.