Define the Quality Assurance Plan. - ANSWER It is a government management tool
establishing staffing, training, pre-award activities, and surveillance activities.
What is the role/responsibility of QC Manager during a design-build project? - ANSWER -
Review and coordinate the design product produced by the contractor's designer of
record
- Report the results of the design quality control activities and outcomes to the QA
- Coordinate with the subcontractors, suppliers and other disciplines to avoid any
interferences/ inconsistencies in the design
Define a Quality Control Plan - ANSWER It is the foundation upon with quality work is
based and outlines planned quality control procedures.
Name the components that must be addressed by the Quality Control Plan - ANSWER -
Table of Contents
- QC Organization
- Name and qualification
- Duties, responsibilities and authorization of a QC personnel
- Outside Organization
- Appointment Letter
- Submittals procedure and initial submittal register
- Testing laboratory information
Test plan and log
Procedure for completing deficiencies/rework items
Documentation procedures
, List of DFOW
Procedure for the Three Phases of Control
Personnel Matrix
Procedure for completion inspection
Name the actions that must be accomplished relative to the QC Plan before construction
can begin. - ANSWER It must be received, reviewed and formally accepted by the
Contracting Officer.
Identify the steps for the "Three-Phase Control", and identify when each is executed. -
ANSWER - Preparatory Phase shall be completed before commencing work on each
DFOW.
- Initial Phase shall be completed at the start of a DFOW.
- Follow-up Phase includes daily checks of the work to ensure continuing conformance
with contract requirements.
What is the purpose of the Post-Award Orientation Conference / Preconstruction
Conference? - ANSWER To review the contract clauses to include accident prevention,
administrative requirements, personnel requirements, and procedural matters.
Why is the Post-Award Orientation Conference / Preconstruction Conference
necessary? - ANSWER Because it lays down the groundwork to set the rules for
administering the contract.
Who schedules, convenes, and conducts the Coordination Meeting or the Mutual
Understanding Meeting (Navy)? - ANSWER Project engineer or the SGE,
AROICC/AREICC and QA Representative.
What are the major purposes of the Coordination Meeting or the Mutual Understanding
Meeting (Navy)? - ANSWER a. To obtain a mutual understanding with the contractor of
his/her role in quality control.
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Easton. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $16.99. You're not tied to anything after your purchase.