NJ QPA STUDY SET TEST // NJ QPA STUDY SET TEST 250+ QUESTIONS AND CORRECT ANSWERS //ALREADY GRADED A+
4 views 0 purchase
Course
NJ QPA STUDY SET0
Institution
NJ QPA STUDY SET0
NJ QPA STUDY SET TEST // NJ QPA STUDY SET TEST 250+
QUESTIONS AND CORRECT ANSWERS //ALREADY
GRADED A+
NJ QPA STUDY SET TEST // NJ QPA STUDY SET TEST 250+
QUESTIONS AND CORRECT ANSWERS //ALREADY
GRADED A+
NJ QPA STUDY SET TEST // NJ QPA STUDY SET TEST 250+
QUESTIONS AND CORRECT ANSWERS /...
NJ QPA STUDY SET TEST // NJ QPA STUDY SET TEST 250+
QUESTIONS AND CORRECT ANSWERS 2023-2025//ALREADY
GRADED A+
What constitutes a capital project? - answer-- Acquisition of land
- Acquisition of major equipment of personal property
- Acquisition of buildings, roads, utilities, or other structures
- Improvements of public works
When can competitive contracting be used? - answer-- Software & hardware
- Homemaker/health services
- Lab testing services
- Emergency medical services
- Contracted food services
- Concessions
- P-Card/ E-Procurement vendor
- Grant writing
- Animal Control
- Property appraisal services
What are the four elements of a contractual situation? - answer-- Capable parties: all persons have
capacity and agency to enter into the contract
- Mutual consent: all persons are entering into a contract voluntarily
- Lawful objective: contract is not criminal, immoral, or illegal
- Sufficient cause to contract: reasons parties entered into a contract
Acceptance of a contract must satisfy what four criteria? - answer-- Voluntary
- Deliberate
- Made by recipient of offer
- Unequivocal and unqualified
,What is a guarantee? - answer-Guarantees reduce a buyer's sense of risk at the time of purchase.
What is a warranty? - answer-Warranties are a promise given by the seller to the buyer that goods are of
a certain quality and will conform to certain standards.
What types of contracts are there? - answer-- Firm Fixed-Price
- Agreement w/ Escalation Provisions (mostly applicable to gas, fuel oil, or solid waste tipping)
- Time & Materials Agreements (hourly rate which and materials at cost)
- Open-Ended Agreements (bids received on a unit basis, must list minimum and maximum)
- Lease Agreements
- Lease w/ Option to Purchase
How long can a typical contract be awarded? - answer-24 months
How long can a PSA contract be awarded? - answer-12 months
How long can a competitive contracting contract be awarded? - answer-Up to 5 years
How long can an insurance contract be awarded? - answer-Up to 3 years
How long can a contract be extended? - answer-Contracts can be extended for one two-year term or
two one-year terms, not to exceed five years total
What are the types of cooperative purchasing systems? - answer-- Cooperative pricing
- Joint purchasing
- Commodity resale system
- County cooperative purchasing contract
- Regional cooperative pricing
,- State contracts
- National co-ops
When do you need to report purchases to State Comptroller? - answer-$2.5 - $12.5 million = 20 business
days AFTER contract is awarded
$12.5 million+ = 30 business days PRIOR to public advertisement
$2.5+ and emergency work = 30 business days AFTER contract is awarded
What is the bid threshold with a QPA? - answer-$44,000
How long before a bid is due should it be advertised? - answer-At least 10 days, can't open on a Monday
or a day after a federal holiday
What was the last time the bid threshold was adjusted? - answer-March 2020, enacted July 2020,
happens every 5 years
What does it mean to be the lowest responsible bidder? - answer-- Responsive: all materials are
included
- Responsible: able to handle the job
Reasons you can reject a bid? - answer-- Lowest bid substantially exceeds cost estimates for G&S
- Lowest bid substantially exceeds appropriations for G&S
- Governing body abandons project
- Governing body substantially updates project specs
- Items are available on state contract
How long should RFP's for competitive contract and municipal solid waste be advertised for? - answer--
Competitive Contract = 20 days
- Municipal Solid Waste = 60 days
, How long does addenda need to be published for? - answer-At least 7 days before bid opening
What is a bid security and what form can they be submitted in? - answer-Intended to ensure the bidder
enters into a contract if they receive the award and will provide a performance bond if required
Can be in the form of a cashier's check, cash, or bid bond in the amount of 10% of the contract amount
up to $20k
What is a consent of surety? - answer-Certificate in the full amount of the bid price from a surety
company
Required for construction projects over $100k
MUST be submitted with a bid
What is a performance bond? - answer-Bond in the amount of 100% of the contract amount
Submitted with the contract (surety guarantees this bond is possible)
Not released until work is final and accepted
What is a maintenance bond? - answer-Submitted once work is completed and accepted
Guarantees against defective quality or materials for period up to 2 years
What are non-curable defects in a bid package? - answer-- Consent of surety (REQUIRED for
construction)
- Bid guarantee
- Statement of ownership
- Iran Disclosure
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller 2024newestexams. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $21.49. You're not tied to anything after your purchase.