Basics covered in Level 1 - -Nuclear Testing
Speedy Moisture
Report Forms
Earthwork has to do with the roadway in what way? - -Earthwork is the excavation
and placement of soils and materials supporting the proposed roadway.
In...
FDOT Earthwork Level 1 Exam Questions With 100%
Correct Answers.
Basics covered in Level 1 - -Nuclear Testing
Speedy Moisture
Report Forms
Earthwork has to do with the roadway in what way? - -Earthwork is the excavation
and placement of soils and materials supporting the proposed roadway.
In Earthwork what is a lift? - -6" of compacted depth at full width
In Earthwork what is a Lot? - -A lot is 1 lift at 500 ft or within compacted area.
Isolated compaction operations are separate lots.
Sampling at the roadway is done for - -Done for base, sub grade, and embankment.
Sampling is determined how - -generated with random numbers usually by a
Verification Inspector
What is important about sampling at the roadway - -Minimum of three representative
sample combined.
What is LIMS? - -Laboratory Info Management System
The proctor theory is when compaction is achieved how - -by inputting energy to
expel air and water in the soil voids
Compaction causes - -An increase in unit weight, decrease in compressibility and
permeability.
, FDOT Earthwork Level 1 Exam Questions With 100%
Correct Answers.
The proctor is determined where and creates what - -In a laboratory and establishes
a density standard to be used on the roadway
Lab proctors are created how - -Material is gathered from the road and prepared with
different amounts of water then placed in molds and hammered
What is a modified proctor used in - -It is used in base, sub grade, MSE wall back fill
materials
Modified proctors are created how - -With a 10lb hammer(rammer) on a 18" drop
with 56 blows per layers with 5 layers in total.
What is a standard proctor used in - -It is used in embankment and structure back fill
materials
Standard proctors are created how - -With a 5.5lb hammer(rammer) on a 12" drop
with 25 blows per layer with 3 layers in total
Comparison between VT and QC density test tolerance - -2 lbs/pcf
What is the STRG - -Sampling, Testing, and Reporting Guide (state wide)
A job guide schedule is - -project specific
The material identification number for embankment in the laboratory is - -004L
The material identification number for embankment in the field is - -004F
The material identification number for base is - -030
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller learndirect. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $10.49. You're not tied to anything after your purchase.