What makes up a quality asphalt mixture? - ANSWER- A quality asphalt mixture is
determined by the constructability, if it conforms to Specifications, and if it satisfies
functional requirements.
CQC - ANSWER- contractor quality control
Superpave - ANSWER- Asphalt mix design system since 1998
QCP - ANSWER- Quality control plan
QCM - ANSWER- Quality control Manual
QC - ANSWER- Quality Control (Contracting Testing and Inspection)
VT - ANSWER- Verification Testing (FDOT or CEI Verification)
CEI - ANSWER- Construction Engineering and Inspection
RT - ANSWER- Resolution Testing (FDOT)
IV - ANSWER- Independent Verification Testing
IA - ANSWER- Independent Assurance Testing
The decision-making authority on a job needs to be given to who? - ANSWER- Needs
to be given to the level closet to the work as specified in the specifications. It ensure a
quick handle on situations and issues.
The governing order of project documents from high (1) to low (7) starts with the highest
being - ANSWER- Special Provisions
The governing order of project documents from high to low (2) - ANSWER- Technical
Special Provisions
The governing order of project documents from high to low (3) - ANSWER- Plans
The governing order of project documents from high to low (4) - ANSWER- Road
design, structures, and traffic operations standards
Page | 1
, The governing order of project documents from high to low (5) - ANSWER-
Developmental Specifications
The governing order of project documents from high to low (6) - ANSWER-
Supplemental Specifications
The governing order of project documents from high to low (7) - ANSWER- Standard
Specifications
What are the key components in a pre-paving conferences? - ANSWER- Key Personnel
(Paving superintendent)
Contractor Input
Agency Input
QC Plan Review
Discuss more specific key topics or issues
Meeting Minutes
Action items (what to do in situations, who to call)
What are the key components in a pre-construction conferences? - ANSWER- Agency
Input (FDOT)
Contractor Input (Including the Prime)
Project Personnel (Upper - Middle management)
Testing
Safety
Utilities
Cities or Municipalities (HOA, school boards)
Suppliers
What causes the compactive effort increase? - ANSWER- Crushed aggregate content
Nominal maximum size
Hardness of the aggrergate
Angularity of aggregate
Less natural sand
High dust content mixes
Gradation of the mix greatly affects compaction
Superpave mixes
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Divinehub. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $10.49. You're not tied to anything after your purchase.