Shear wall - ANSWER A wall designed to resist lateral forces parallel to the plane Of a
wall.
The private garage shall be separated from the dwelling unit and
its attic area by means of a minimum ____ inch gypsum. - ANSWER 1/2"
Become familiar with all types Of construction I-V.
Become fam...
North Carolina General Contractors Exam
CORRECT QUESTIONS & ANSWERS(GRADED A)
Shear wall - ANSWER A wall designed to resist lateral forces parallel to the plane Of a
wall.
The private garage shall be separated from the dwelling unit and
its attic area by means of a minimum ____ inch gypsum. - ANSWER 1/2"
Become familiar with all types Of construction I-V.
Become familiar with Table 601 for the exam. - ANSWER
Bolt heads must not be closer than ____ to the edge Of fireproofing. - ANSWER 1"
The height of the parapet firewall shall not be less than ____ above the point where the roof surface and
the wall intersect. - ANSWER 30"
The clearance between the ends of combustible members in a
firewall must be ____. - ANSWER 4"
You may use combustible roof insulation if the roof covering is
____ ____to the insulation. - ANSWER applied directly
NO. 18 SWG steel tie wires spaced ____ on
center. - ANSWER 24"
Be able to determine finish requirements using this table.
, 805.1.1; Know the requirements for fire-blocking to be constructed using combustible materials. -
ANSWER
Combustible insulating boards not more than ____ thick and
covered with finish flooring are permitted where attached directly to a non-combustible floor assembly
or to wood subflooring attached to sleepers. - ANSWER 1/2"
Ramps used as a part of a means of egress shall have a running
slope Of not steeper than ____. - ANSWER 1:12 horizontally
Ramp landings ____. - ANSWER 60" long
Handrail height between ____. - ANSWER 34"-38"
Round handrails maximum diameter ____. - ANSWER 2"
Handrail should have at least ____ clearance. - ANSWER 1-1/2"
All platforms and mezzanines more than ____ high must have
a ____ guardrail. - ANSWER 30", 42"
Required guards shall not be less than ____ high. - ANSWER 42"
Guardrail balusters shall not allow a sphere greater than ____ in
diameter to pass between them. - ANSWER 4"
Emergency escape and rescue minimum net clear opening of ____. - ANSWER 5.7 s.f.
Maximum height from floor not greater than ____. - ANSWER 44"
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Lecchris. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $9.99. You're not tied to anything after your purchase.