Exam (elaborations)

CE-611 project Planning & control ch 6 study guide

 2 views  0 purchase
  • Course
  • CE-611 project Planning & control ch 6
  • Institution
  • CE-611 Project Planning & Control Ch 6

CE-611 project Planning & control ch 6 study guide • So far we have assumed “time” to be the driving force of our schedule • If we have time everything is possible right? It takes 2 days to erect a wall if we have the 2 days then everything is great. • But what happens if you have the...

[Show more]

Preview 4 out of 53  pages

  • November 1, 2024
  • 53
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • CE-611 project Planning & control ch 6
  • CE-611 project Planning & control ch 6
avatar-seller
Academia199
CE-611
project
Planning &
CHAPTER 6 – Resource Allocation &
Resource Leveling
PART 1 – Introduction to Resource
Allocation
control
Professor Hanna

,Lets look back at what we have

•So far we have assumed “time” to be the driving force of
our schedule
• If we have time everything is possible right? It takes 2 days to erect a wall
if we have the 2 days then everything is great.
•But what happens if you have the 2 days but no workers? Or
no concrete?
•Time is no longer our leading resource

, Resource

•When a network is developed for a project, the logic presumably reflects
sequences of the activities as they must take place, without regard to
limitations imposed by the availability of resources.
•In practice this is not typically the case, sometimes you schedule the
most expensive activities towards the end of the job in order to have
some “cash-flow” before you get to those activities.
•Other times you want to order all the steel together to get a better price
when you buy in “bulk”. There are many reasons why you schedule
something out of order but the most important one is “Resource
Allocation”.

, Resource

•Invariably, the logic initially incorporated in a network already
reflects the fact that some resources must be efficiently utilized.
•Regardless of how you want to schedule the job you should
always allocate time for the steel (or other materials) to be
fabricated/delivered

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller Academia199. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $13.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

81989 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$13.49
  • (0)
  Add to cart