In a Gantt chart, thick black bars represent milestones achieved in a
project. - answer False
Which of the following techniques involve doing activities in parallel that
one would normally do in sequence? - answer Fast tracking
Which of the following is an output of schedule control? - answer
Lessons-learned reports
After working with key stakeholders to define activities and calculate their
resources, the next process in project time management is to: - answer
estimate the duration of activities
_____ is the amount of time an activity can be delayed from its early start
without delaying the planned project finish date. - answer Total slack
A Tracking Gantt chart is based on the percentage of work completed for
project tasks or the actual start and finish dates. - answer True
A difference between the Program Evaluation and Review Technique
(PERT) and critical path method (CPM) is that: - answer PERT uses
different duration estimates whereas CPM uses one specific duration
estimate
In project time management, the ultimate goal of _____ is to provide a
basis for monitoring project progress for the time dimension of the
project. - answer developing a schedule
The final process in project time management is developing the schedule.
- answer False
, Critical chain scheduling assumes that resources multitask and maximizes
multitasking. - answer False
A disadvantage of using Gantt charts is that they do not provide a
standard format for displaying planned project schedule information. -
answer False
The critical path is the _____ path through a network diagram, and it
represents the _____ amount of slack or float. - answer longest; shortest
The critical path on a project can change as the project progresses. -
answer True
In project time management, one should control the schedule before
estimating the duration for each activity. - answer False
The technique for making cost and schedule trade-offs to obtain the
greatest amount of schedule compression for the least incremental cost is
known as _____. - answer crashing
The technique of fast tracking can result in lengthening the project
schedule. - answer True
Which of the following is a similarity between scope control and schedule
control? - answer Both are portions of the integrated change control
process under project integration management
In a critical path analysis, the shortest path is what drives the completion
date for the project. - answer False
A backward pass through the network diagram determines the early start
and early finish dates for each activity. - answer False
_____ states that work expands to fill the time allowed. - answer
Parkinson's Law
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller BRAINBOOSTERS. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $16.99. You're not tied to anything after your purchase.