OV - 6 aspects of project performance to be manage - Answers-1.Costs
2.TimeScale
3.Quality
4.Scope
5.Risk
6.Benefits
OV - 5 characteristics of a project - Answers-1.Change
2.Temporary
3.Cross functional
4.Unique
5.Uncertainty
OV - 4 integrated elements on which Prince2 is based - Answers-1.principles
2.themes
3.processes
4.the project environment
OV - 7 Benefits of using Prince2 - Answers-1.can be applied to any projects
2. common vocabulary & approach
3.integrates easily with industry specific model
4.ensure management by exception to make efficient use of executives time
5.ensure focus on the continuing viability of the projet
6.lot of accredited training & consultancy org
7.explicit definition of roles & responsability
OV - Customer/Supplier context of Prince2 project - Answers-...
OV - 7 Principles - Answers-1.continuous business justification
2.learn from previous experience
3.defined & agreed roles & responsabilities
4.management by stages
5.management by exception
6.focus on the delivery of products
7.tailoring of methodology
OV - Difference between a project & a programme - Answers-...
OV - 5 characteristics of a project (detailled) - Answers-1.Change : projects are the
means to introduce changes
2.Temporary : one desired change has been implemented business as usual resume
(start & end)
,3.Cross functional : projects invovle a team of people with different skills working
together to introduce a change outside of the team. Often cause strains since each has
a different perspective
4.Unique : every project is unique. different team, customer, location
5.Uncertainty : threats & opportunities. More risks.
OV - Definition of a project - Answers-a temporary organisation that is created for the
purpose of delivering one or more business products according to an ageed Business
Case
OV - 7 themes - Answers-1.Business Case : why
2.Organisation : who
3.Quality : What
4.Plans : How? How much? When?
5.Risk : what if?
6.Change : what's the impact
7.Progress : where are we know? Where are we going? Should we carry on?
BC - Purpose of the BC them - Answers-is to establish mecanism to judge whether the
project is (and remains) desirable, viable and achievable as a means to support
decision making in its (continued) investment
BC - How the BC supports the continued biz justif principle - Answers-by documenting
the business justification in the business case describing the reasons for the project
based on estimated cost, risk & expected benefits
BC - Difference between output, outcome & benefit - Answers-output : any of the
project's specialist products (tangible or not); (ex : New Sales System)
outcome : the result of the change derived from using the project's output (ex:Sales
Order are processed faster)
benefit: measurable improvement resulting from an outcome that is perceived as an
advantage by one or more stakeholders (Costs are reduce by 15%)
BC - Purpose of BC & Benefit Review Plan - Answers-BC: used to document the
justification for the undertaking of a project based on the estimated costs against the
anticipated benefits to be gained & offset by any associated risks.
BFR : how & when a measurement of the achievement of the project's benefit, expected
by senior user, can be made
BC - Recommanded composition of a BC (9) - Answers-1. Exec Summary
2. Reasons
3. Business options
4. Expected benefits
5. Expected dis-benefits
6. Timescale
7.Costs
, 8.Investment appraisal
9.Major risks
OR - Roles in OR - Answers-Project Board (3)
Executive
Snr User
Snr Supplier
Project Assurance (Business, User & Supplier)
Project Manager
Change Authority
Project Support
Team Managers
Team Members
OR - Purpose of OR theme - Answers-to define & establish the project structure of
accountability & responsability
OR - in which process OR them is applied & which roles are responsible for this -
Answers-...
OR - the 3 projects interest & how these are represented within the three levels of the
project mgmt team structure - Answers-Business, User & Supplier
OR - how the four levels of the project mgmt structure apply to the process model -
Answers-...
OR - Project Board Role + 4 chars - Answers-Executive + Snr Supplier + Snr User
has authority & responsability for the project within the instructions (prj mandate) set by
corporate or program mgmt
Authority; Credibility; Ability to delegate; Availbility
OR - Difference between project stakeholders & decision makers - Answers-Project
stakeholders need to be informed
Decision makers need to be on the board
OR - purpose of the communication mgmt strategy - Answers-Contains a description of
the means & frequency of communication to parties both internal & external to the
project.
It facilitate the engagement with stakeholders through the establishment of a controlled
& bi-directional flow of information
OR - 4 levels of mgmt - Answers-Corporate => program mgmt
Directing => project Board
Managing => Project Manager
Delivering =>Team Manager
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller GEEKA. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $12.99. You're not tied to anything after your purchase.