100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
NCIDQ IDPX EXAM LATEST 2024 ACTUAL QUESTIONS AND CORRECT VERIFIED ANSWERS|ALREADY GRADED A+|GUARANTEED TO PASS CONCEPTS $17.99   Add to cart

Exam (elaborations)

NCIDQ IDPX EXAM LATEST 2024 ACTUAL QUESTIONS AND CORRECT VERIFIED ANSWERS|ALREADY GRADED A+|GUARANTEED TO PASS CONCEPTS

 7 views  0 purchase
  • Course
  • NCIDQ IDFX
  • Institution
  • NCIDQ IDFX

NCIDQ IDPX EXAM LATEST 2024 ACTUAL QUESTIONS AND CORRECT VERIFIED ANSWERS|ALREADY GRADED A+|GUARANTEED TO PASS CONCEPTS

Preview 4 out of 50  pages

  • October 19, 2024
  • 50
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
book image

Book Title:

Author(s):

  • Edition:
  • ISBN:
  • Edition:
  • NCIDQ IDFX
  • NCIDQ IDFX
avatar-seller
juliusmigwi
NCIDQ PRACTICUM EXAM LATEST 2024
ACTUAL QUESTIONS AND CORRECT VERIFIED
ANSWERS|ALREADY GRADED A+|GUARANTEED
TO PASS CONCEPTS




Why does the HVAC system need to be balanced at the end of a commercial project?



A. To verify that air quality levels are within the design specifications

B. To detect significant air leaks in the ductwork.

C. To adjust airflow at each device location to meet the criteria in the engineer's design

D. To determine that each office is receiving the amount of outside air required by the design -
✔✔ANSWER✔✔The correct answer is C. Balancing the HVAC system is the process of measuring air flow
from diffusers and making adjustments to avoid hot and cold spots within a space. It does not measure
air quality, ductwork leaks or outside air.



P1 Project Coordination



The typical chronological order of system installation in new commercial construction is:



A. HVAC, Plumbing, Electrical

B. Electrical, Plumbing, HVAC

C. Plumbing, HVAC, Electrical

D. Electrical, HVAC, Plumbing - ✔✔ANSWER✔✔The correct answer is C. Once the interior of a building is
sufficiently protected from the weather, the waste lines and water supply lines of the plumbing system
are installed and, if specified, the pipes for the sprinkler system. The major part of the work for the HVAC
system is carried out, including the installation of boilers, chillers, cooling towers, pumps, fans, piping,
and ductwork. Electrical, communications, and control wiring are routed through the building.

,P3 Building Systems and Integration



In which situation would an interior designer use a construction change directive?



A. To request an electrical contractor not listed by the contractor in the bid [tender] documents

B. To request pricing for an additional receptacle per the client's request

C. To provide additional dimensions to the contractor regarding a receptacle location

D. To relocate an electrical receptacle because of revised furniture plans - ✔✔ANSWER✔✔The correct
answer is D. Issuing a change order is the best way to communicate a change to the construction
documents after the contract has been awarded.



P6 Contract Administration



At project closeout, what documentation MUST contain the certification of flameproofing for finishes?



A. Maintenance manuals for furnishings and finishes

B. Guarantees or warranties for furnishings and finishes

C. Record documents for finish applications and furniture installations

D. Certificates of completion for finish applications and furniture installations - ✔✔ANSWER✔✔The
correct answer is B. Flameproofing would fall into the category of guarantees and warranties as it would
affect the performance if the product as well as the product's warranty.



P4 Product and Material Coordination



Why are addenda issued?



A. To provide additional information not included in the bid package

B. To inform potential bidders about acceptable alternates

C. To obtain additional information

, D. To request a change during construction - ✔✔ANSWER✔✔A. To provide additional information not
included in the bid package



What does an interior designer look for in a job site visit during contract administration?



A. Conformance to safety procedures

B. Conformance to applicable codes

C. Compliance with contract documents

D. Compliance with the project schedule - ✔✔ANSWER✔✔The correct answer is C. Ensuring compliance
with the contract documents is an important part of interior design project management.



P6 Contract Administration



Using a standard form of agreement, who owns the contract documents, construction drawings, and
specifications produced by your office for a specific project?



A. The client and the firm share ownership because they both need the contract documents.

B. The client owns the documents because they paid the design fee and signed a contract with your
firm.

C. The design firm owns the documents because there is no separate agreement assigning rights to the
client.

D. The design firm and lead designer share ownership because the project design is considered
intellectual property. - ✔✔ANSWER✔✔The correct answer is C. Unless noted under a separate
agreement, the drawings and documents prepared by a design firm remain the property of the design
firm and cannot be used for any purpose other than the completion of the project.



P7 Professional and Business Practices



Which of the following has the GREATEST impact on the effectiveness of an HVAC system?



A. Rooftop chiller size

, B. Wall insulation type

C. Window treatments

D. Occupancy load - ✔✔ANSWER✔✔The correct answer is D. The mechanical engineer will size the
chiller based on the area to be conditioned, the type of window glazing, and the rating of the wall
insulation; however, if the occupancy load is greater than what was identified on the plan, the HVAC
system will not function as intended.



P3 Building Systems and Integration



Which of the following is a non-loadbearing, fire-resistant wall assembly?



A. 5/8" [16 mm] gypsum wallboard on 2" x 6" [50 mm x 150 mm] wood studs

B. 1/2" [13 mm] gypsum wallboard on 2 1/2" [65 mm] metal studs

C. Structural clay tile

D. Glass block - ✔✔ANSWER✔✔The correct answer is D. Glass block can only be used in non-
loadbearing applications.



P3 Building Systems and Integration



What portion of a contract typically outlines the designer's responsibilities to the client?



A. Scope of services

B. Project description

C. Terms and conditions

D. Compensation schedule - ✔✔ANSWER✔✔A.

Scope of services



In which space is emergency lighting REQUIRED?



A. Elevators

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller juliusmigwi. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $17.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

73918 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$17.99
  • (0)
  Add to cart