Foundations (multiple choice) Exam Review
PRINCE2 and
Questions ( PRojects IN Controlled
Answers | 100%Environments)
Pass | Graded
FoundationA+and |Practitioner
PRINCE2 Exam
Course Title and Number: PRINCE2
Exam Title: PRINCE2 Midterm and Final
Exam Date: Midterm and Final Exam 2024- 2025
Instructor: [Insert Instructor’s Name]
Student Name: [Insert Student’s Name]
Student ID: [Insert Student ID]
Examination
180 minutes
Instructions:
1. Read each question carefully.
2. Answer all questions.
3. Use the provided answer sheet to mark your responses.
4. Ensure all answers are final before submitting the exam.
5. Please answer each question below and click Submit when you
have completed the Exam.
6. This test has a time limit, The test will save and submit
automatically when the time expires
7. This is Exam which will assess your knowledge on the course
Learning Resources.
Good Luck!
Need Writing Help? We've Got You Covered! ✍️
100%
NO AI or Plagiarism Usage Guaranteed🎯
💬 Chat with us here: 📧 Hybridgrades101@gmail.com
,Read All Instructions Carefully and Answer All the
Questions Correctly Good Luck: -
PRINCE2 is based on there being a
A. Project environment
B. Working environment
C. Customer/programme environment
D. Customer/supplier environment - Answer>> D
In which activity of controlling a stage would a team
manager review the quality register?
A. Receive completed work packages
B. Authorise a work package
C. Take corrective action
D. None of the above - Answer>> D
Which management products do not record benefits
tolerance?
A. Project plan
B. Business case
C. Work package
D. Project product description - Answer>> A, C, D
As we are in the starting up a project process, the
project manager does not need to consider any
corporate, programme management or customer
standards that will need to be applied to the project yet
A. True
B. False - Answer>> B
Which of the following statements are true?
A. The businesss justification must be reviewed and
updated throughout the project
Need Writing Help? We've Got You Covered! ✍️
100%
NO AI or Plagiarism Usage Guaranteed🎯
💬 Chat with us here: 📧 Hybridgrades101@gmail.com
,B. Management actions to ensure project outcomes are
achieved must be defined
C. A benefits management approach is intended to
ensure that benefits are realised
D. A business case can take many forms - Answer>> A,
B, C, D
Team managers should not produce a team plan in
parallel with the PM producing the next stage plan.
A. True
B. False - Answer>> B
Which of the following is not an activity of the closing a
project process?
A. Hand over products
B. Prepare planned closure
C. Recommend project closure
D. Authorise project closure - Answer>> D
Which of the following is a purpose of the project brief?
A. Provides a full and firm foundation for deliver of the
project products
B. Provides a contract between the PM and the project
board
C. Provides a full and firm foundation for the initiation
of the project
D. The project brief is maintained through the project
lifecycle - Answer>> C
What is the first step in the recommended risk
management procedure? - Answer>> Identify
What statements about a project stakeholder is
correct?
Need Writing Help? We've Got You Covered! ✍️
100%
NO AI or Plagiarism Usage Guaranteed🎯
💬 Chat with us here: 📧 Hybridgrades101@gmail.com
, 1. A stakeholder is anyone who thinks they might be
effected by a project
2. Stakeholders require equal amounts of engagement
by the PM team
3. Stakeholders remain unchanged throughout the
project
4. A stakeholder may be internal or external to the
organisation - Answer>> 1 and 4
Identify the missing work in the following sentence.
A purpose of the [?] theme is to control any
unacceptable deviations from the project's objectives
A. Change
B. Plans
C. Progress
D. Risk - Answer>> C. A purpose of the progress theme is
to provide mechanisms to monitor progress against the
allowed tolerances, and the controls to escalate to the
next level should any forecast suggest that one or more
tolerances are to be exceeded
Which is a minimum requirement for applying the
organisation theme?
A. To define the project assurance role of team
managers
B. To combine roles, where possible, to simplify the
organisation
C. To appoint a business change manager as senior
user when the project is part of the programme
D. To define the approach to engaging with
stakeholders - Answer>> D
Need Writing Help? We've Got You Covered! ✍️
100%
NO AI or Plagiarism Usage Guaranteed🎯
💬 Chat with us here: 📧 Hybridgrades101@gmail.com
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller StarScoreGrades. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $14.99. You're not tied to anything after your purchase.