Which of the following takes place when IT projects are managed properly? - Answer-Employee productivity loss is minimized.
As a project manager, you complete a Statement Of Work (SOW) at the end of the initiating phase of a project. What does a SOW outline? - Answer-The requirements for each pr...
CIW IBA Chapter 10 Review Exam
Questions with Correct Answers
Which of the following takes place when IT projects are managed properly? - Answer-
Employee productivity loss is minimized.
As a project manager, you complete a Statement Of Work (SOW) at the end of the
initiating phase of a project. What does a SOW outline? - Answer-The requirements for
each project task to ensure that the project objectives are met
What can you do during the executing and controlling phases of a project to discuss
progress, and to respond to project issues and unanticipated developments? - Answer-
Plan and schedule meetings with team members.
Which result reflects an IT project that is properly managed? - Answer-Employee
productivity loss is minimized.
Which of the following is an interactive Web-based seminar or training session that is
typically conducted in a one-way format, from speaker to participants with limited
audience participation? - Answer-Webinar
A drawback of Webinars is that they: - Answer-may require multiple presentations if
participants are located in different time zones.
Receiving clear, detailed objectives and instructions so that you can provide the
appropriate services and products can be considered which of the following? - Answer-
An IT right
Milestones can add significant value to project scheduling because: - Answer-they can
become the points at which the project team or project stakeholders evaluate the
project's progress and make decisions that may affect the status of the project going
forward.
During which project management phase should you develop a project schedule and
assemble the project team? - Answer-The planning phase
What is the term for a Web site and network used only by employees within a
company? - Answer-Intranet
You want to attend a training session remotely. The presenter has recommended an
application for you to download that uses VoIP audio technology so you can interact
with the presenter and the other participants. Which Web-based system does this
scenario describe? - Answer-Web conference
, During which project management phase should you troubleshoot problems and take
corrective measures to ensure that all objectives are being met? - Answer-The
controlling phase
What is the project triangle? - Answer-The relationship among time, money and scope
in completing a project
In many cases, project teams are created and developed with people who have different
perspectives and priorities. Why is it important for a project manager to have the ability
to develop and manage teams? - Answer-To help team members complete the project
schedule within the project constraints
If you were a project manager, which of the following documents would be the most
helpful in evaluating project risks and determining whether you should escalate
concerns to managers or executives outside the project team for resolution? - Answer-
An issues log
Project tasks take longer to complete, requiring more company resources and money. -
Answer-Project tasks take longer to complete, requiring more company resources and
money.
What is the purpose of a needs analysis? - Answer-To identify the problems or
requirements that the project must resolve or address
Your company wants to simplify the customer support process for its distributors by
enabling them to obtain company forms and reports online. You and your Web team are
in charge of implementing this capability. Which Web-based system should you
implement? - Answer-Extranet
What is the term for the goals and tasks of a project, and the work required to complete
them? - Answer-Scope
Project managers must balance three elements that compose the project triangle. You
are a project manager who is halfway through a project when your customer contacts
you to say that he has been authorized to provide additional funds for the project. How
will this most likely affect other elements of the project? - Answer-Project scope will
increase.
Which document lists the planned dates for performing tasks and meeting goals
identified in the project plan? - Answer-Project schedule
What is a project constraint? - Answer-A factor, such as budget or time, that limits a
project manager's options
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller lectknancy. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $12.49. You're not tied to anything after your purchase.