What equipment is used to drive piles? - ANSWER 1. Gravity
Hammers
2. Open-end and closed end - diesel hammers
3. Air and steam hammers
4. hydraulic Ham...
NICET LEVEL 2 IN HIGHWAY
CONSTRUCTION 2024 EXAM
QUESTIONS WITH VERIFIED CORRECT
ANSWERS || ALREADY GRADED A+
<UPDATED VERSION>
What equipment is used to drive piles? - ANSWER ✔ 1. Gravity
Hammers
2. Open-end and closed end - diesel hammers
3. Air and steam hammers
4. hydraulic Hammers
What is the wave equation for driving piles? - ANSWER ✔ between 2
and 10 blows per inch
When pre-boring when should you stop? - ANSWER ✔ within 5 feet of
estimated pile tip
When do you check pile alignment? - ANSWER ✔ before the last 5' of
the pile is driven
The axial alignment should be within how many inches of the
longitudinal axis, when driving piles? - ANSWER ✔ within 1/4" per
foot
What timber piles should not be used? - ANSWER ✔ When checks
cracks are wider than 1/2"
, How many splices per pile is allowed? - ANSWER ✔ 2 spices
What length of splice is not allowed? - ANSWER ✔ less than 10'
What length is allowed for non spliced piles? - ANSWER ✔ 60'
When should precast piles be rejected? - ANSWER ✔ When cracks,
spalls, or internal defects are visible
What is spalling? - ANSWER ✔ Breakdown of concrete via natural
weathering or chemical reaction
What is concrete honey combing? - ANSWER ✔ Defect in concrete
caused in insufficient consolidation
What is concrete scaling? - ANSWER ✔ Flaking or peeling of hard
concrete caused by freeze/thaw
how long should pre-cast piles be left in their forms? - ANSWER ✔ no
less than 7 days
What is the dynamic load test? - ANSWER ✔ Method to assess a pile
bearing capacity by applying a load onto pile head
When does dynamic load test start? - ANSWER ✔ 24 hours after pile
has been driven
What are the requirements for the dynamic load test? - ANSWER ✔
Redrive pile for a maximum of 3" and a maximum of 20 blows or
refusal
What is the static load test? - ANSWER ✔ Measures the response of the
pile under applied load
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller ProfBenjamin. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $8.49. You're not tied to anything after your purchase.