100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
ISQS 4350 (Burns) Exam 2 Questions and Answers | 100% Pass $12.49   Add to cart

Exam (elaborations)

ISQS 4350 (Burns) Exam 2 Questions and Answers | 100% Pass

 3 views  0 purchase
  • Course
  • ISQS
  • Institution
  • ISQS

ISQS 4350 (Burns) Exam 2 Questions and Answers | 100% Pass Which of the following statements is false? a. Probability distributions for PERT activity durations are represented by use of the Beta distribution. b. A forward pass through a project network diagram determines the early start and e...

[Show more]

Preview 4 out of 67  pages

  • October 6, 2024
  • 67
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • ISQS
  • ISQS
avatar-seller
EmillyCharlotte
EMILLYCHARLOTTE 2024/2025 ACADEMIC YAER
©2024 EMILLYCHARLOTTE. ALL RIGHTS RESERVED
FIRST PUBLISH SEPTEMBER 2024

ISQS 4350 (Burns) Exam 2 Questions
and Answers | 100% Pass

Which of the following statements is false?




a. Probability distributions for PERT activity durations are represented by use of the

Beta distribution.

b. A forward pass through a project network diagram determines the early start and

early finish dates for each activity.

c. To complete a project it is necessary to complete all tasks on all paths through the

project network.

d. The critical path is the series of activities that determine the earliest time by which a

project can be started.

e. Both c. and d. are false statements. - Answer✔✔-d. The critical path is the series

of activities that determine the earliest time by which a project can be started.

As the project manager for a software development project, you are helping to develop

the project schedule. You decide that writing code for a system should not start until

users sign off on the analysis work. Further, you decide that testing of a module (an

object, class) will not commence until the entire module has been coded and compiled.

What type of dependency is this?



a. There is no dependency.
1/67

,EMILLYCHARLOTTE 2024/2025 ACADEMIC YAER
©2024 EMILLYCHARLOTTE. ALL RIGHTS RESERVED
FIRST PUBLISH SEPTEMBER 2024
b. External

c. Mandatory

d. Discretionary

e. Internal - Answer✔✔-c. Mandatory

The district magistrate of Arkham City has decided to rebuild the busiest road in the city.

She plans to close the street for the duration of the work, causing immense

inconvenience to the people who typically use the road. The project has 3 parallel paths

defined as the following:

Path A-B-C-H will take 14 days.

Path A-F-G-H will take 28 days.

Path A-D-E-H will take 20 days.

Given the information on hand, which of the following statements is true?



a. Path A-D-E-H is the critical path.

b. Path A-B-C-H is the critical path.

c. Path A-F-G-H has the largest slack time.

d. Path A-F-G-H is the critical path.

e. Path A-D-E-H has the largest slack time. - Answer✔✔-d. Path A-F-G-H is the

critical path.

The ________ calculates the critical path and determines how long an activity can be

delayed without delaying the project.




2/67

,EMILLYCHARLOTTE 2024/2025 ACADEMIC YAER
©2024 EMILLYCHARLOTTE. ALL RIGHTS RESERVED
FIRST PUBLISH SEPTEMBER 2024
a. concurrent pass

b. forward pass

c. backward pass

d. parallel pass - Answer✔✔-c. backward pass

Which of the following is not one seven processes that make up the PMBOK knowledge

area known as time (schedule) management?



a. Sequence activities

b. Define activities

c. Control activities

d. Plan schedule management

e. Monitor activities - Answer✔✔-e. Monitor activities

Which PMBOK activity is responsible for determining activity resource requirements,

and for determining a resource breakdown structure?



a. Estimate activity durations

b. Develop schedule

c. Plan schedule management

d. Estimate activity resources

e. Define activities - Answer✔✔-d. Estimate activity resources

Rose leads the advertising of an innovative product, Teckos, just launched by her

company. She has determined the advertising for Teckos is an individual project

3/67

, EMILLYCHARLOTTE 2024/2025 ACADEMIC YAER
©2024 EMILLYCHARLOTTE. ALL RIGHTS RESERVED
FIRST PUBLISH SEPTEMBER 2024
consisting of 7 activities. Information pertinent to these activities is included in the table

that follows. Using a Gantt chart, determine the earliest completion time for the project.



a. 10 weeks

b. 13 weeks

c. 11 weeks

d. 12 weeks - Answer✔✔-d. 12 weeks

For any activity that has one or more predecessors, the ________ time is always the

largest early finish of any of its predecessors. If the early finish times of an activity's

predecessors were 55, 40 and 35, then this time would be the largest of these three

early finish times or 55.



a. late finish

b. early start

c. early finish

d. late start - Answer✔✔-b. early start

In project time management, which of the following processes involve calculating the

number of work periods that are needed to complete individual tasks?



a. Defining activities

b. Estimating activity durations

c. Controlling schedule


4/67

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller EmillyCharlotte. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $12.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

80796 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$12.49
  • (0)
  Add to cart