100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
PMP Mock Test 1 Questions And Answers Latest Updates 2024/2025 $14.99   Add to cart

Exam (elaborations)

PMP Mock Test 1 Questions And Answers Latest Updates 2024/2025

 1 view  0 purchase
  • Course
  • PMP Mock
  • Institution
  • PMP Mock

PMP Mock Test 1 Questions And Answers Latest Updates 2024/2025

Preview 3 out of 18  pages

  • October 1, 2024
  • 18
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • PMP Mock
  • PMP Mock
avatar-seller
Schoolflix
PMP Mock Test 1 Questions And Answers
Latest Updates 2024/2025

In the middle of the execution phase for a big project, a new stakeholder who
was unfamiliar with the project joined the board of directors and is
influencing the decisions made in the project. This change is impacting the
project's progress. What should the project manager do first?

A. Inform the client about the change.

B. Update the risk register with the new risk.

C. Present the Project to the stakeholder.

D. Revise the project schedule. ANS✔✔ C.

Presenting the project to the new stakeholder is the most proactive and
constructive step to take when a new influential stakeholder joins the project
in the middle of the execution phase. By doing so, the project manager can:

- Provide the new stakeholder with a comprehensive understanding of the
project, its objectives, scope, and current status.

- Share the project's progress, achievements, and challenges.

- Address any questions or concerns the new stakeholder may have.

- Establish open communication and build a working relationship with the
stakeholder.

This approach helps ensure that the new stakeholder is well-informed and
can make informed decisions that are aligned with the project's goals and
objectives. It also demonstrates transparency and a willingness to
collaborate. While options A, B, and D may be necessary at some point,
presenting the project to the new stakeholder should be the first step to
establish effective communication and engagement, which can help mitigate
potential disruptions to the project caused by their influence.



In the past year, a company paid US$60,000 to an external subcontractor for
an ongoing project. The project manager has been asked to evaluate if the


2024

,project can be delivered more cost effectively this year by using internal
labor. The project manager used an optimistic term of 4 months, a
pessimistic term of 6 months, and a most expected term of 5 months, and
has concluded that the service can be delivered with the following resources:
Two engineers (monthly salary of US$700 each), One project manager
(monthly salary of US$1,600), Additional estimated monthly expenses of
US$2,000 The project manager used the program evaluation and review
technique (PERT) to calculate the savings if the project is delivered with in-
house resources. How much money will the project manager estimate the
company can save?

A. $35,000

B. $20,000

C. $40,000

D. $30,000 ANS✔✔ A.

Calculate the estimated duration: Estimated Duration = (4 + 4 * 5 + 6) / 6 =
(4 + 20 + 6) / 6 = = 5 months



Cost of two engineers for 5 months = US$7,000

Cost of one project manager for 5 months = US$8,000

Additional monthly expenses for 5 months = US$10,000

Total = US$25,000



Estimated Savings = US$60,000 - US$25,000 = US$35,000



A project to build a new energy plant was just completed. However, a few
days before operation of the plant, the local community protested and closed
access to the plant. They argue that an important natural reserve was
impacted and prior consultation was not done by the project team. What
should the project manager verify first?

A. Stakeholder engagement plan.



2024

, B. Cost-benefit analysis

C. Business case

D. Risk management plan ANS✔✔ A.

Stakeholder engagement plan: The stakeholder engagement plan outlines
how the project team will engage and communicate with various
stakeholders throughout the project's lifecycle. In this case, the local
community's concerns indicate that there might have been issues with
stakeholder engagement and consultation. Verifying the stakeholder
engagement plan will help the project manager determine whether the
appropriate steps were taken to engage with the local community, address
their concerns, and ensure compliance with any necessary regulations or
consultation requirements.



During an iteration review session, some product features are at risk of being
canceled due to high operational costs when the product is launched into a
production environment. What type of analysis should the project lead have
conducted to avoid this situation?

A. Benefits analysis

B. Capacity analysis

C. Gap analysis

D. Risk analysis ANS✔✔ D.

Risk analysis involves identifying, assessing, and mitigating risks that may
impact the project or product. In this case, the risk of high operational costs
when launching the product into a production environment is a significant
concern. By conducting a risk analysis, the project lead could have identified
this risk, assessed its likelihood and impact, and developed mitigation
strategies to address it.



A project manager is assigned to a technical research project. The project
team has already been assigned, and the main subject matter expert (SME)
sends the project manager a list of the technical skills required for the
execution of this project. What should the project manager do next?



2024

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller Schoolflix. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $14.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

77333 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$14.99
  • (0)
  Add to cart