WGU C722- Project Management (PHEO) - Objective Assessment Study Guide 100% ACCURATE $14.99   Add to cart

Exam (elaborations)

WGU C722- Project Management (PHEO) - Objective Assessment Study Guide 100% ACCURATE

 0 view  0 purchase
  • Course
  • WGU C722
  • Institution
  • WGU C722

A firm begins its strategic business initiative of developing a new business model that will allow the firm to deliver an efficient, tailored service to its customers. To accomplish this, the firm initiates a business management project. Which aspect of project management applies to this firm's pro...

[Show more]

Preview 4 out of 66  pages

  • September 17, 2024
  • 66
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • wgu c722
  • WGU C722
  • WGU C722
avatar-seller
shantelleG
WGU C722- Project Management (PHEO) -
Objective Assessment Study Guide 100%
ACCURATE
A firm begins its strategic business initiative of developing a new business model that will allow the firm
to deliver an efficient, tailored service to its customers. To accomplish this, the firm initiates a business
management project. Which aspect of project management applies to this firm's project?



Independent operations

Interdependent tasks

Regulatory concept

External environment - ANSWER Interdependent Tasks



A firm begins its strategic business initiative of developing a new business model to enhance its
competitiveness. What can be identified as a strategic business initiative for this firm?



Timely payment of liabilities

Liaison with regulatory agencies

Improvement in product design

Environmental scanning - ANSWER Improvement in product design



A firm begins a strategic business initiative of developing a new business model that will allow the firm
to deliver an efficient, tailored service to its customers.



Director of operations

Production supervisor

Project sponsor

Financial controller - ANSWER Project sponsor

, Which group is included in the five process groups?



Risk process group

Closing process group

Communication process group

Quality process group - ANSWER Closing process group



What does PRINCE2 stand for?



PRoject INsights for CompEtitiveness



PRojects IN a Competitive

Environment



PRoject INsights and CompEtencies



PRojects IN a Controlled

Environment - ANSWER PRojects IN a Controlled Environment



Which PMBOK process group is described as the delivery part of project management where the main
activity happens?



Planning

Executing

Controlling

Closing - ANSWER Executing

,Which advantage does the functional (departmentalized) organizational structure provide for a firm with
multiple projects?



Lines of authority are clear.



The project customer is the only focus.



It is efficient for collaboration and cooperation between departments.



Each project is managed holistically. - ANSWER Lines of authority are clear.



Which two organizations are examples of organizations with the functional organizational structure?



Microsoft



The U.S. Department of State



The U.S. National Aeronautics and Space Administration (NASA)



The U.S Department of Energy



Google Inc. - ANSWER (1) The U.S. Department of State and (2) The U.S Department of Energy



An organization expects to use a project management office (PMO) to support multiple projects that will
be implemented within a projectized organizational structure. Which implied effect is a benefit to this
organization?



Project team members retain their functional responsibilities.



Project team members become full-time employees.

, Project team members gain access to the newest technologies and skill sets.



Project team members gain access to historical data from other projects. - ANSWER Project team
members gain access to historical data from other projects.



Regardless of the organizational structure used to manage a project, an organization elects to use a
project management office (PMO). Which benefit will this organization gain?



Projects will coordinate resource usage by monitoring the status of shared resources.



Projects will define the organization's corporate strategy in the project charter.



Projects will receive a 10% managerial reserve fund to cover warranty back charges.



Projects will eliminate the costs incurred from having to follow corporate procedures. - ANSWER Projects
will coordinate resource usage by monitoring the status of shared resources.



During a certain project phase, specific blueprints are drawn and approved, materials and labor costs are
estimated, prototypes are created, and work activities and tasks are identified. Also, quality
expectations, measurements, and costs are defined. During which project phase do these activities
occur?



Defining

Planning

Executing

Closing - ANSWER Planning



Place the project activities in order of occurrence from first (1) to last (5). - ANSWER (1) Collecting
customer requirements (2) Developing the work breakdown structure (3) Working to produce project
deliverables (4) Customers evaluating the project outcomes (5) Capturing lessons learned

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller shantelleG. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $14.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

78140 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$14.99
  • (0)
  Add to cart