100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
CMP 101 Final Exam Questions and Answers All Correct $12.59   Add to cart

Exam (elaborations)

CMP 101 Final Exam Questions and Answers All Correct

 5 views  0 purchase
  • Course
  • CMP 101
  • Institution
  • CMP 101

CMP 101 Final Exam Questions and Answers All Correct What are the components of the construction contract? - Primary Specifications - Secondary Specifications - None of these - General Specifications - Plans and Specifications - Answer-Plans and Specifications Which of the following con...

[Show more]

Preview 3 out of 16  pages

  • September 1, 2024
  • 16
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • CMP 101
  • CMP 101
avatar-seller
Scholarsstudyguide
CMP 101 Final Exam Questions
and Answers All Correct
What are the components of the construction contract?
- Primary Specifications
- Secondary Specifications
- None of these
- General Specifications
- Plans and Specifications - Answer-Plans and Specifications

Which of the following construction plans will show light fixtures and their switches?
- Mechanical
- Electrical
- None of these
- Civil
- Architectural - Answer-Electrical

A Construction Manager would perform the following functions as a part of 'Monitoring
Project Performance'
- Ensure that all portable toilets are functioning for workers to use.
- Ensure the architect has completed all construction drawings
- Ensure the project cost is within owner's budget
- Ensure that work orders are given to sub-contractors
- Ensure the project is proceeding as per the schedule - Answer-- Ensure the project
cost is within owner's budget
- Ensure the project is proceeding as per the schedule

Details regarding concrete beams that support the loads on the building will be shown
on the __________________plans
- Architectural
- Plumbing
- Civil
- Structural
- Electrical - Answer-Structural

Once the owner occupies the home, they can call the contractor to come in and fix any
issues as long as the home is under the ________________stage
- Commissioning
- Final Inspection
- Design
- Warranty

,- None of these - Answer-Warranty

In order to start pouring concrete for concrete footings, following steps must be
complete:
(SELECT ALL THAT APPLY)
- Installation of CMU foundation wall
- Installation of Floor Joists
- Footing Formwork Installation
- Footing Rebar Installation
- Installation of Underground Utilities
- Excavation - Answer-- Footing Formwork Installation
- Footing Rebar Installation
- Installation of Underground Utilities
- Excavation

Electrical plans are labelled in the title box as _________________for the first electrical
plan:
- A1
- M1
- E1
- P1
- S1 - Answer-E1

In this type of contract, the owner and architect provide the constructor the estimated
quantities of defined items of work.
- Value-Added Contract
- Unit-Price Contract
- Cost-Plus Fee
- Lump-Sum Contract
- None of these - Answer-Unit-Price Contract

The amount that a buyer pays to purchase a house is known as _____________
- Value
- Cost
- None of these
- Price - Answer-Price

Design and Construction Phases can overlap in the following project delivery method
- Integrated Project Delivery
- CM Agency
- At-Risk CM
- All of these
- Design - Build - Answer-All of these

Each site build project is a ________________________.
- duplicate of the last one using the same plans and specs.

, - civil endeavor
- Prototype
- A and B are correct
- A and C are correct - Answer-Prototype


As a construction manager for a road construction project, you would perform the
following tasks:
(Select all that apply)
- Hire skilled workers to perform the construction work
- Manage the finances to ensure the project makes profit.
- Operate all road building equipment
- Ensure the project is completed on time - Answer-- Hire skilled workers to perform the
construction work
- Manage the finances to ensure the project makes profit.
- Ensure the project is completed on time

For CMP101, what are the 2 types of construction?
- Building and Non-building construction
- Residential and Commercial construction - Answer-Building and Non-building
construction

GC is an acronym for which one of the following?
- Generic Construction
- General Contractor
- Genoa City
- General Construction
- None of these - Answer-General Contractor

On a NON-RESIDENTIAL construction project, the Owner may directly hire the
following entities:
(SELECT ALL THAT APPLY)
- Electrical Engineer
- Architect
- Masonry Contractor
- Prime Contractor
- Construction Manager - Answer-- Architect
- Construction Manager

On a residential construction project from the following construction activities, what
activity would be performed first
- Backfilling around foundation
- Installing Formwork for foundation
- Does not matter - Either one of these can be performed first.
- Pouring concrete for foundation
- Excavation for foundation - Answer-Excavation for foundation

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller Scholarsstudyguide. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $12.59. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

78310 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$12.59
  • (0)
  Add to cart