PMP Practice Exam Questions with Complete
Solutions
Which document defines how a project is executed, monitored and controlled,
and closed? Correct Answer-Project Management Plan
Which changes occur in risk and uncertainty as well as the cost of changes as the
life cycle of a typical proje...
PMP Practice Exam Questions with Complete
Solutions
Which document defines how a project is executed, monitored and controlled,
and closed? Correct Answer-Project Management Plan
Which changes occur in risk and uncertainty as well as the cost of changes as the
life cycle of a typical project progresses? Correct Answer-Risk and uncertainty
decrease; the cost of changes increases.
Which tool or technique is used in the Plan Scope Management process?
Correct Answer-Expert Judgment
Which tool or technique is an examination of industry and specific vendor
capabilities? Correct Answer-Market Research
An input used in developing the communications management plan is:
Correct Answer-Enterprise Environmental Factors.
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis
(FTA), and trend analysis are examples of which tool or technique? Correct
Answer-Analytical Techniques
The Perform Quality Assurance process occurs in which Process Group?
Correct Answer-Executing
Enterprise environmental factors are an input to which process? Correct
Answer-Plan Scope Management
, PMP Practice Exam Questions with Complete
Solutions
Which process develops options and actions to enhance opportunities and
reduce threats to project objectives? Correct Answer-Plan Risk Responses
The process of establishing the policies, procedures, and documentation for
planning, developing, managing, executing, and controlling the project schedule
is known as: Correct Answer-Plan Schedule Management
Which input to the Manage Stakeholder Engagement process is used to
document changes that occur during the project? Correct Answer-Change Log
An input to the Plan Stakeholder Management process is: Correct Answer-
stakeholder Register
An input to the Plan Cost Management process is: Correct Answer-The
Project Charter
A technique used to determine the cause and degree of difference between
baseline and actual performance is: Correct Answer-Variance Analysis
The process of identifying and documenting project roles, responsibilities,
required skills, and reporting relationships and creating a staffing management
plan is known as: Correct Answer-Plan Human Resource Management
Which type of dependency is legally or contractually required or inherent in the
nature of work and often involves physical limitations? Correct Answer-
Mandatory
, PMP Practice Exam Questions with Complete
Solutions
During which process does a project manager review all prior information to
ensure that all project work is completed and that the project has met its
objectives? Correct Answer-Close Project or Phase
An input to the Manage Project Team process is: Correct Answer-Work
Performance Reports
Which input provides suppliers with a clear set of goals, requirements, and
outcomes? Correct Answer-Procurement Statement of Work
A large portion of a projects budget is typically expended on the processes in
which Process Group? Correct Answer-Executing
"A project manager providing information to the right audience, in the right
format, at the right time is an example of which type of communication?"
Correct Answer-Effective
Scope, schedule, and cost parameters are integrated in the: Correct Answer-
Performance Measurement Baseline.
A project in which the scope, time, and cost of delivery are determined as early
as possible is following a life cycle that is: Correct Answer-Predictive
, PMP Practice Exam Questions with Complete
Solutions
What is the schedule performance index (SPI) if the planned value (PV) is $100,
the actual cost (AC) is $150, and the earned value (EV) is $50? Correct
Answer-0.5
Which item is an input to the Define Activities process? Correct Answer-
Scope Baseline
When alternative dispute resolution (ADR) is necessary, which tool or technique
should be utilized? Correct Answer-Claims Administration
Which quality management and control tool is useful in visualizing parent-to-
child relationships in any decomposition hierarchy that uses a systematic set of
rules that define a nesting relationship? Correct Answer-Tree diagram
The only Process Group that comprises processes that typically occur from the
beginning to the end of the project life cycle is: Correct Answer-Monitoring
and Controlling.
Organizational theory is a tool used in which Project Human Resource
Management process? Correct Answer-Plan Human Resource Management
Which tools or techniques are used in the Plan Schedule Management process?
Correct Answer-Expert judgment, analytical techniques, and meetings
A project manager is appointed full-time to a project and is given full-time
administrative staff and full-time project team members. This situation
describes which type of organizational structure? Correct Answer-Projectized
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller TheeGrades. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $24.49. You're not tied to anything after your purchase.