CCM EXAM QUESTIONS AND ANSWERS
What does commercial general liability cover? - Answers -Bodily injury, property
damage and false advertsing
What is a FORMAL DEMAND for compensation by the contractor? - Answers -Claim.
The phrase formal demand is what separates this from a change order.
If a structure is being built on a former brown field site. What type of insurance coverage
should the CM recommend? - Answers -Pollution Legal Liability Coverage
What is a cost plus contract? - Answers -A contract that covers project costs and
contractor markup. Aka time and materials.
Why do owners like cost plus GMP agreements? - Answers -The time of performance is
reduced.
T/F, One purpose of the general conditions is to provide a procedure for executing
changes in the work scope in a fair and equitable manner? - Answers -True
What project delivery method puts the most risk on the owner? - Answers -Multi Prime
What does substantial completion Mean? - Answers -The project is ready for occupancy
in accordance with its intended purpose.
If a contractor defaults in construction performance and a performance bond is used
who pays for a new contractor or compensated the owner? - Answers -The surety
company
What is the purpose of public building statutes? - Answers -Protect public funds
Ensure continuation of free enterprise
Where should project dimensions, manufacturing conventions and special fabrication
instructions be included? - Answers -Shop Drawings
A contingency amount of 15% would be most appt at which phase of a project? -
Answers -Design
What is the formula for earned value in an earned value analysis? - Answers -EV = % of
project complete * project budget
What is the formula to calculate CPI (Cost Performance Index)? - Answers -CPI =
EV/actual cost
, Does a CPI ratio higher than 1 indicate that the project is doing well or not? - Answers -
Well
What takes into account capital operating and maintenance costs to verify that the most
effective design solution has been achieved? - Answers -Value engineering analysis
What would be considered an impact cost when estimating change orders? - Answers -
Changes in sequence of work
What estimating technique is used during the conceptual phase of design, utilizing
actual costs from similar, previously performed projects? - Answers -Analogous
estimating
A derived performance model that can be generated from a cost loaded schedule is a? -
Answers -Cash flow curve
A cost which is very difficult if not impossible to capture accurately through a change
order is known as what type of cost? - Answers -Impact
What type of estimate is performed regularly during the construction phase? - Answers -
Progress estimate
When the CM performs forward pricing, what factor should be considered when
evaluating production rates? - Answers -Labor agreements
At the pre design stage of a project what should the normal expected design
contingency that an estimator should add to the total estimated construction costs? -
Answers -15%-25%
The project cost management system should best be aligned with which of the
following: CSI Format, CPM, WBS, GMP - Answers -WBS (work breakdown structure)
The dollar and time amount allocated by the owner for a project is defined as: - Answers
-A budget
A CMs response to an owner's request for qualifications and/or proposal can be
incorporated into the agreement between the owner and CM to: - Answers -Identify the
scope and quality of services the CM is to provide.
When the owner assigns risk to the CM, the CM has fiduciary responsibility to what
party or parties? - Answers -The owner only
What is the term used to describe work that is not conforming to contract specs that the
contractor must complete prior to final payments? - Answers -Punchlist
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller GEEKA. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $12.49. You're not tied to anything after your purchase.