COSC 475 Select all correct answers. What are the the essential skills for critical thinking - logical analysis - creative thinking - decision making - control calculation - Answer- - logical analysis - creative thinking - decision making what are the 4 level of scheduling - Answer- 1...

[Show more]

Preview 2 out of 8  pages

  • August 25, 2024
  • 8
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • cosc 475
  • logical analysis
  • COSC 475
  • COSC 475
avatar-seller
Freshy
COSC 475
Select all correct answers. What are the the essential skills for critical thinking

- logical analysis
- creative thinking
- decision making
- control calculation - Answer- - logical analysis
- creative thinking
- decision making

what are the 4 level of scheduling - Answer- 1. proposal
2. pre-construction
3. construction
4. look ahead

what level fits best with this image
- level 1 - Answer- - summarize overall project
- start & finish dates for major phases & key milestones

what level fits best with this image: level 2 - Answer- - preconstruction
- starts to focus on the primary activities and task by trade, looks at critical
components

what level fits best with this image : level 3 - Answer- - critical path

in this course, a critical path method is utilized, and will have a start and finish dates
and links for all activities. also called - Answer- level 3

in this course for level 3 construction the duration is set to - Answer- not be longer
than 10 days

Activities are represented daily and often called a three or four week "___" ecasue it
has weekly input from all trades - Answer- look-ahead

T/F: tasks can be in any phase of the project or any schedule level - Answer- True

Generally tasks can be in any phase of the project, to define a tasks two factors are
required - Answer- task-dependent, resource-dependent

a zero duration on the project that are important to watch - Answer- milestones

a task with fixed dates and duration, should not have predecessors or successors -
Answer- deadlines/constraints

what are the five keys to successful teams? - Answer- - established roles and
responsibilities
- defined goals and objectives

, - know the system in which you are working
- identify problems and barriers
- know your people

how can quantity of work be examined - Answer- SF, LF, EA, CY

define the term
- the average efficiency of a standard crew in a task - Answer- production rate

weather, congested space, area layout, material handling, crew expertise, safety
requirements, complexity are all factors for ___ - Answer- productivity

work hours = - Answer- quantity of work/production rate

adjusted work hours = - Answer- work hours x productivity factor

activity duration = - Answer- adjusted work hours / hours per workday

gantt charts - Answer- bars show the relationship between tasks

T/F: Testing assumption is key in the logical analysis phase of critical thinking -
Answer- TRUE

in project management describe activitiesthat depend upon one another to proceed.
These dependencies amongactivities will determine the order in which the project
plan proceeds.Predecessors in project management are activities that must begin
orend before a successor task can proceed. - Answer- predecessors and successors

which scheduling relationship types do we use in this class? - Answer- Finish to
Start,
Start to Start, Finish to Finish

which scheduling link extends duration without any critical paths? - Answer- float

which scheduling link has two activities that have delay but it not careful could
become critical - Answer- lags

which scheduling link used level 3 scheduling where you put a specific date for that
activity to start of finish, if not it is considered a delay - Answer- constraints

SS, FF, FS are also called - Answer- logic relationship

the amount of time required to complete a task in work days - Answer- duration

activities with no float connected to determine the amount of time to complete the
project - Answer- critical path

float is called - Answer- free float, total float

which software calls the schedule level tasks - Answer- MP

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller Freshy. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $10.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

78310 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$10.49  1x  sold
  • (0)
  Add to cart