All of the following are included in an Agile project charter, except for which one?
a. Detailed project scope
b. Expected ROI
c. Signature and date
d. Project goals and objectives: correct answer- a) Detailed project scope
Agile team members have identified a risk in a project and are not able to resolve it due to lack of
expertise. You, as a Agile project manager, decided to contract with a third party for resolving the risk.
Which of the following risk response strategies have you applied?
a. Accept
b. Avoid
c. Transfer
d. Mitigate: correct answer-c) Transfer
When the customer is thinking and explaining something one way and the team takes it in a different
way. This is referred to as which of the following?
a. The gulf of understanding
b. The gulf of misunderstanding
c. The gulf of Agile
d. The gulf of evaluation: correct answer-a) The gulf of understanding
An Agile team working together on a project are sitting in a big meeting room. In the room, John was
discussing with Kim about a security loophole while implementing the code design for a module. In
between, Harry, who was listening to their discussion gets an idea on the improvement of current code
design and notes it down for further design discussion meeting with architects. He asks John and Kim to
park this code implementation for a while and requests them to continue code development of the
remaining module.
According to the given scenario, this is referred to as which of the following?
a. Osmotic communication
b. Emotional intelligence
CMGT 410
,CMGT 410
c. Nonverbal communication
d. Mirroring: correct answer- b) Emotional intelligence
As an Agile project manager, you want to perform a review of your project from several different
characteristics. You would like to review what worked on the project and what needed improvement.
Which of the following will you use to accomplish the task?
a. Kano analysis
b. MoSCoW
c. Shu Ha Ri
d. SWOT analysis: d) SWOT analysis
Using the following values: earned value = 8,000 planned value = 4,000, actual cost = 3,000, calculate
CV (cost variance).
a. 5,000
b. 4,000
c. 1,000
d. 2,000: a) 5,000
Which of the following is a performance measure, used for evaluating gain or loss generated on an
investment relative to the amount of money invested?
a. IRR
b. INVEST
c. ROI
d. NPV: c) ROI
All of the following are examples of special causes, except for which one?
a. Machine malfunctioning
b. Measurement errors
c. Faulty controllers
d. Computer crashing: b) Measurement errors
CMGT 410
,CMGT 410
In a planning poker session, the cards used are presented with which of the following series for assessing
story points?
a. Arithmetic progression
b. Fibonacci
c. Even
d. Odd: b) Fibonacci
A technique in which multiple team members focus collectively on resolving a specific impediment is
referred to as:
a. Tailoring
b. Grooming
c. Swarming
d. Refactoring: c) Swarming
What is the primary purpose of the retrospective meeting?
a. Discuss what went well, what didn't got so well, and what improvements could be made
immediately in the next iteration.
b. Identify what was learned during the project/program.
c. Demonstrate the completed work to the customer for gaining their feedback and for encouraging
collaboration
d. Discuss and review team practices openly and assess how the team is working together.: a) Discus
what went well, what didn't got so well, and what improvements could be made immediately in the
next iteration.
According to the Agile Manifesto, which of the following is an accurate practice?
a. Contract Negotiation over Customer Collaboration
b. Comprehensive Documentation over Working Software
c. Individuals and Interactions over Processes and Tools
d. Following a Plan over Responding to Change: c) Individuals and Interactions over Processes and
Tools
CMGT 410
, CMGT 410
The Shu Ha Ri model depicts the maturity of learning and application in a team environment. What is the
meaning of the word Sha Ha Ri?
a. Leave, be the rule; learn, follow the rule, detach, break the rule
b. Detach, break the rule; leave, be the rule; learn, follow the rule
c. Learn, follow the rule; detach, break the rule; leave, be the rule
d. Detach, break the rule; separate, be the rule; learn, follow the rule: c) Learn, follow the rule;
detach, break the rule; leave, be the rule
A planning is done at three distinct horizons using which of the following?
a. Wireframe
b. Prototyping
c. Progressive elaboration
d. Kano analysis: c) Progressive elaboration
As an Agile project manager, you are planning a seating arrangement for your project team. You want
that the team sits together in the work area and sees each other. What is the purpose of this arrangement?
Helping the product owner to attend the daily stand-ups
Making the optimum use of available space
Helping a team to see what the other person is doing
Helping in osmotic communication: d) Helping in osmotic communication
You ask the customer to give out fake amount to individual business features to better understand the
project's goal. This is referred to as which of the following?
a. Dot voting
b. Monopoly money
c. MoSCoW
d. 100-point method: b) Monopoly money
In a discussion between two Agile team members, one of the team mem- bers is showing positive
gestures, nodding his head, and asking questions. This is an example of which of the following?
a. Emotional intelligence