CON 2370 Exam With Verified Questions
and Answers
You are the contracting officer for a services contract that contains options. You send the
preliminary notice of your intent to extend the contract five days after the deadline outlined in
the options clause.Which one of the following statement...
You are the contracting officer for a services contract that contains options. You send the
preliminary notice of your intent to extend the contract five days after the deadline outlined in
the options clause.Which one of the following statements is correct? - answer✔✔WRONG
You no longer have the right to exercise the option using a unilateral modification.
Which one of the following statements about solicitations using SAP is correct? - answer✔✔The
basis on which award will be made must be stated
Which one of the following mandatory Government sources is the first priority for satisfying a
requirement for services? - answer✔✔inventories of the requiring agencies
You just made a purchase in the amount of 22,300. You solicitated quotations orally from four
local sources. Which of the following statements is correct regarding providing notice to the
unsuccessful suppliers? - answer✔✔notice to unsuccessful suppliers will only be given if
requested
You have just been informed that a purchase order you recently awarded for commercial services
is no longer needed and must be cancelled. The order was accepted in writing by the contractor.
Which one of the following statements is true? - answer✔✔The purchase order is considered
cancelled if the contractor accepts the Government's written cancellation and does not claim
costs were incurred.
You are the contracting officer for a noncommercial supply contract valued at $155,600. Which
one of the following actions would be executed using a bilateral modification -
answer✔✔Making a negotiated equitable adjustment
You have a requirement for a one-time purchase with an estimated value of $180,700. You are
not required to synopsize this contract action. Which one of the following describes the
competition requirement for this acquisition? - answer✔✔Quotes must be solicited from at least
three sources
You have a requirement for repair parts to support routine maintenance services at the shop on
your base. The parts are sold to the general public and are used for nongovernmental purposes.
The estimated dollar value of the acquisition is $625,000.Which one of the following statements
is true? - answer✔✔The use of simplified acquisition procedures is authorized
Which one of the following market research results would NOT support a commercial item
determination? - answer✔✔The part sold to the general public needs' extensive modifications not
customarily available in the commercial marketplace.
You have a requirement for help desk support with an estimated value of $450,000. Market
research shows there are numerous potential offerors that are competitive in terms of market
prices, quality, and delivery. The list of potential offerors includes 6 small businesses and 4 large
businesses.Which one of the following statements is correct? - answer✔✔The entire acquisition
must be set aside exclusively for small business
You are the buyer for a construction requirement with an estimated value of $75,000. A notice of
the proposed contract action is required.Which one of the following solicitation methods must be
used? - answer✔✔Written Solicitation
You are the contracting officer for a construction requirement with an estimated value of
$20,600. Access to the written solicitation will not be provided in the GPE, and none of the
exceptions in FAR 5.202 apply.Which one of the following correctly describes the requirement
for publicizing this proposed contract action? - answer✔✔notice of the solicitation, or a copy of
the solicitation, must be posted in a public place
Which one of the following is NOT correct regarding documenting the award of a buy using
SAP? - answer✔✔Records of oral price quotations must be established to clearly reflect the
appropriateness of the award decision.
You are the contracting officer for a firm-fixed-price purchase order for commercial services
with a value of $1,425,000. Your customer has notified you that one of the contractually required
reports accepted by the Government was submitted five days late. You investigate and verify that
the report was submitted late.Which one of the following statements regarding the
nonconforming performance is FALSE? - answer✔✔The government must pay for the
reperformance of the nonconforming service because the report was accepted.
You are the contracting officer for a firm-fixed-price supply contract valued at $195,400.Which
one of the following statements about contract closeout is correct? - answer✔✔WRONG
The contract is considered closed once you receive evidence of receipt of property and final
payment
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Brightstars. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $11.49. You're not tied to anything after your purchase.