CMIT Exam (200 Multiple Choice) Questions and Answers.
A CM's role and responsibilities are governed solely by the Owner/CM Agreement.
True False - Correct Answer True
There are two basic forms of CM, agency and at-risk. Each form provides for the basic services
of construction management practice. However, there are some key differences. Which of the
following do not apply to both CM forms?
A) Both forms provide advice to the owner on constructibility, budget and the schedule.
B) Both require that the liabilities and risks assumed by the parties be clearly understood,
coordinated, and stated in the respective contracts.
C) Both forms allow the CM to function in an advisory role for the entire engagement of the CM.
D) Services can vary based on the contractual relationships of the parties and the risks that are
assumed. - Correct Answer C) Both forms allow the CM to function in an advisory role for the
entire engagement of the CM.
Construction management had its beginnings in the early to mid-1960's. Which of the following
factors contributed to the initial use of this delivery system?
A) The need to reduce the overall time and cost associated with project delivery.
B) The increasing cost of money and the unpredictability of project funding streams.
C) The changing role of the general contractor and the increasing numbers of specialty trade
contractors.
D) All of the above. - Correct Answer D) All of the above.
The General Services Administration was the first federal agency to use construction
management. - Correct Answer True
The General Services Administration, the Department of Health, Education and Welfare (now
HHS), and the Veterans Administration ran into similar difficulties in the use of construction
management. Which of the following was/were common problems for all three agencies?
A) Funding restrictions
B) Claims
C) Change conditions
D) All of the above - Correct Answer D) All of the above
CMAA was formed and incorporated 1982 with its primary focus being the growth and
development of the construction management profession. - Correct Answer True
The CMAA Construction Management Standards of Practice is intended as a guide to the range
of services that constitute professional construction management. They seek to meet the
documented need for definitions of what construction management services are, without unduly
structuring the methodologies by which those services are provided by the CM. - Correct
Answer True
,The goals of the Construction Management Association of America (CMAA) include:
A) Setting standards and developing contract documents for construction management practice.
B) Expanding the understanding of the construction management concept and its use in the
marketplace.
C) Advocacy for construction management in the legislative, regulatory, and judicial arenas of
federal, state, and local governments.
D) All of the above. - Correct Answer D) All of the above
The fact that an individual is certified or licensed in any other profession does not, per se,
establish him/her as a qualified CM.
True False - Correct Answer True
Certification as a CM means the construction management practitioner has "state of the art"
knowledge and capability to practice construction management.
True False - Correct Answer False
Recruiting and training are business matters and normally do not involve ethical concerns.
True False - Correct Answer False
Construction management is a concept that is susceptible to overselling.
True False - Correct Answer True
Failure to provide quality services is a business and not an ethical question.
True False - Correct Answer False
Contracting for adequate fees is both a business and an ethical issue.
True False - Correct Answer True
The ethics of the CM profession focus primarily on a CM's relationships in dealing with its
clients.
True False - Correct Answer True
The possible approaches for delivering a project are virtually unlimited. A key reason for such
variations is:
A) The different roles that can be assumed by project participants.
B) Different forms of contracts and methods of compensation that can be used.
C) The different levels of care, responsibility, and risks assumed by the parties involved.
D) All of the above. - Correct Answer D) All of the above
The traditional delivery system is characterized by executing the major phases of a project in:
A) An overlapping concept
B) A linear sequence
C) A fast track method
D) All of the above - Correct Answer B) A linear sequence
, A key advantage of the traditional delivery approach is:
A) With the traditional delivery system, the cost of the construction phase is known before
construction starts.
B) Facility features are fully determined & specified.
C) When the construction contract is signed, the major risk belongs to the contractor.
D) All of the above - Correct Answer B) Facility features are fully determined & specified.
Design-build and at-risk construction management delivery systems allow the option to fast-
track or phase a project.
True False - Correct Answer True
Most definitions of construction management are similar. However, a contractual definition is not
known until:
A) The legal form of the CM contract is chosen.
B) The specific scope of services to be provided is identified.
C) The relationship of the CM to others and the risks and authority assumed by the parties are
clearly defined.
D) All of the above - Correct Answer D) All of the above
21.
In a CM-at-Risk arrangement once construction begins and the CM converts from the
professional advisory role of a CM to the contractual role of a general contractor, the CM has no
implied duties of loyalty and care to the owner.
True False - Correct Answer True
The agency CM does not perform design or actual construction work.
True False - Correct Answer True
Under the CM-at-Risk delivery method, the owner usually must deal with the hybrid of a
construction manager and a general contractor.
True False - Correct Answer True
Under a CM-at-risk contract, which of the following statements are true?
A) The CM, in most cases, holds the trade and/or specialty contracts.
B) The CM has the right to enforce the schedule, pay the trade or subcontractors, and terminate
them if such action becomes necessary.
C) On some CM-at-Risk contracts, the CM has the option of performing portions of the work
with its own resources (unless prohibited by law on certain public projects).
D) All of the above - Correct Answer D) All of the above
In considering the differences between agency CM and CM-at-Risk, which one of the following
statements is NOT true?
A) With the CM-at-Risk, the CM is responsible for means, methods, and sequencing of work.
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Lectjoe. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $17.99. You're not tied to anything after your purchase.