What are the four teams that comprise the overall Project Team? - CORRECT ANSWER
Owner, Design, Installation, and Management
Who would belong to the Design team? - CORRECT ANSWER Anyone with
Consultant in their title except the moving consultant
Which groups make up the Management Team? - CORRECT ANSWER Developer,
Construction Manager, and Building Management Agency
The End-User, Facility Manager and Building Committee comprise which team within the
Project Team? - CORRECT ANSWER Owner
Which group represent the generic roles that are important to the Project process? -
CORRECT ANSWER Project Managers, Designers and Installers
Which project characteristics must be considered in order to determine which method is
best suited for a particular project? - CORRECT ANSWER Schedule, Size, Type,
Complexity, and Procurement Requirements
What is an important aspect of funding that has a direct impact on the project process
and design/installation? - CORRECT ANSWER Technical Support Funding
,LATEST CTS EXAM PREP (INFOCOMM)
PRACTICE 2024-2025 QUESTIONS WITH
VERIFIED SOLUTIONS
Whether a construction project is large or small, which milestones must be achieved in a
typical schedule? - CORRECT ANSWER Programming, Building Design, AV Bid, and
Move-In
What type of project is a typical Consultant-Led Design-Bid-Build contract structure good
for? - CORRECT ANSWER Long term projects with extended project cycles
What is the risk in using an OFE/Integrator Installed contract structure? - CORRECT
ANSWER System and infrastructure design and facility functionality may suffer
What are some of the important project scope and size considerations in selecting an AV
provider? - CORRECT ANSWER Financial Stability, Current Workload, and Company
Credentials
What type of document typically includes Project Size Requirements, Corporate Profile,
Team Personnel, and Warranty Response Time? - CORRECT ANSWER RFQ
a significant difference between the Two-Envelope Bid
Method and the Qualifications- Based Selection Method? - CORRECT ANSWER
Negotiate with the highest ranking firm to finalize the contract
What is one of the disadvantages of contracting the AV integrator to the electrical
,LATEST CTS EXAM PREP (INFOCOMM)
PRACTICE 2024-2025 QUESTIONS WITH
VERIFIED SOLUTIONS
subcontractor? - CORRECT ANSWER More layers of responsibility and
communication
When conducting a complete project bid process, what milestone follows the issuing of
the RFP? - CORRECT ANSWER Pre-Bid Meeting
Under what circumstances would you likely use an A305-1986 form? - CORRECT
ANSWER Scoring responses to an RFQ
What is the ideal way to contract an AV integrator? - CORRECT ANSWER Directly to
the Owner
The process of identifying the activities that end-users need to perform, and developing
the functional descriptions of your systems is referred to as:? - CORRECT ANSWER
Needs Analysis
What is the main task of the third Step of the Program Phase of a Project? - CORRECT
ANSWER Conducting program meetings
What should be included in the written Program Report? - CORRECT ANSWER ...A
conceptual and functional system description
, LATEST CTS EXAM PREP (INFOCOMM)
PRACTICE 2024-2025 QUESTIONS WITH
VERIFIED SOLUTIONS
The more accurate means to estimate dimensions of a commercial space during a site
inspection would be to? - CORRECT ANSWER Count Ceiling Tiles in a drop tile
instalation
A client requires a new boardroom. The sales person and engineer are sent to the
premises to measure the facility and talk to the client. At this stage they should be
performing a _ - CORRECT ANSWER Needs Analysis
Sightlines for audience viewing in a given presentation space can be improved by: -
CORRECT ANSWER Providing a sloped, or stepped, seating arrangement
After presenting a proposal, what is the correct plan of action for following up with the
client? - CORRECT ANSWER Regularly, until a decision is made
AV professionals determine the end user's needs by examining three things: the
required applications, the tasks, and the: - CORRECT ANSWER Functions to support
the applications
When working with a client to design an AV solution for a new conference center, the
client requests a detailed budget for the equipment and installation. What phase is the
project in? - CORRECT ANSWER Design phase
The HDTV aspect ratio is equal to which of the following? - CORRECT ANSWER
1.78:1
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller TestBankcenter. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $18.49. You're not tied to anything after your purchase.