CMIT Exam Questions and answers |
Latest 2024/25 RATED A+
The contract documents for a project should be written primarily to protect the interest of
ii ii ii ii ii ii ii ii ii ii ii ii ii ii
the CM. - False
ii ii ii ii ii ii
The owner, CM and Designer are less likely to be involved in disputes with the Contractor if
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
a contract is awarded to the lowest bidder. - False
ii ii ii ii ii ii ii ii ii ii ii ii
ii Use of standard forms of agreement will always result in fewer disputes? - False
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
After the owner accepts a cm's proposed GMP as contemplated by the CMAA CM at Risk
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
Series documents, the responsibilities and duties of the CM are essentially the same as if
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
the Owner and CM were using the AIA GMP documents. - False
ii ii ii ii ii ii ii ii ii ii ii ii ii ii
In the CMAA CM at Risk series documents, the CM may perform part of the work if the CM
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
so chooses? - False
ii ii ii ii ii ii
Contractors generally believe the Designer acts independently and in the joint interests of
ii ii ii ii ii ii ii ii ii ii ii ii ii
the Owner and Contractor when making decisions regarding contract claims and change
ii ii ii ii ii ii ii ii ii ii ii ii
orders. - False
ii ii ii ii ii
The CMAA standard forms of agreements(Agency- or CM at risk series) are the best
ii ii ii ii ii ii ii ii ii ii ii ii ii ii
documents for an Owner to use on all design and construction projects. - False
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
The CMAA contract documents were written primarily to protect the interest of the CM. -
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
False
ii
In the CMAA Agency series the Designer is entitled to object to provisions of Construction
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
Management Plan as prepared by the CM. - True
ii ii ii ii ii ii ii ii ii ii ii
When providing services specified in CMAA document A-1, the CM may have a fiscal
ii ii ii ii ii ii ii ii ii ii ii ii ii ii
liability for negligent preparation of the cost estimates. - True
ii ii ii ii ii ii ii ii ii ii ii ii
In the CMAA CM at Risk Series documents, the CM is the Owner's principle agent until a
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
GMP is accepted by the Owner. - True
ii ii ii ii ii ii ii ii ii ii
If an Owner uses the CMAA documents A-4, the Owner may be obligated to compensate
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
the Designer as an additional service for site visits requested by the CM. - True
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
If a Designer uses the CMAA A-4 contract document instead of the AIA B-141/CM
ii ii ii ii ii ii ii ii ii ii ii ii ii ii
document, the Designer's exposure to professional liability during the construction phase
ii ii ii ii ii ii ii ii ii ii ii
is reduced. - True
ii ii ii ii ii ii
, The CM has the autority on behalf of the owner to disapprove or reject work and to revoke,
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
alter, enlarge or relax and requirements of the contract documents. - False
ii ii ii ii ii ii ii ii ii ii ii ii ii ii
The Owner has the obligation to exercise its right to stop work when it would be to the
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
benefit of the Contractor and the Contractor requests the Owner to exercise that right. -
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
False
ii
All communications to the Designer and Owner from the Contractor must be submitted
ii ii ii ii ii ii ii ii ii ii ii ii ii
through the CM - True
ii ii ii ii ii ii ii
The Owner shall pay all charges to utility owners for any of the connections to the work. -
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
False
ii
The Contractor has no obligation to provide others contractors working on the site safe
ii ii ii ii ii ii ii ii ii ii ii ii ii ii
access to the site. - False
ii ii ii ii ii ii ii ii
The Contractor's duty and responsibility for safety and protection of the work extends to
ii ii ii ii ii ii ii ii ii ii ii ii ii ii
the issue of Notice of Substantial Completion. - False
ii ii ii ii ii ii ii ii ii ii ii
If the Contractor causes damage to the work property of another contractor working on the
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
site, the Contractor shall seek to remedy the situation through the CM. - False
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
If it become apparent that the Contractor's schedule will not be met and it is due to the fault
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
of the Contractor, the Contractor agrees that it will increase the number of employees and
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
such crafts to regain the lost schedule progress, increase the number of work hours per
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
shifts, or shifts per a work day, or work days per week to regain the lost schedule progress.
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
- True
ii ii ii ii
ii Unit priced items do not include overhead and profit in the unit price. - False
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
When the delay is due to cause beyond the control of the Owner and the Contractor, an
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
extension of contract time in the amount equal to the item lost on the critical path shall be
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
the Contractors' sole and exclusive remedy for such delay. - True
ii ii ii ii ii ii ii ii ii ii ii ii ii
A CM's liability is determined solely by whether or not the CM performed according to the
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
required standard of care. - False
ii ii ii ii ii ii ii ii
A cost overrun in the delivery of a project is by definition a breach of the CM's duty of care
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
to the Owner. - False
ii ii ii ii ii ii ii
ii It is illegal to discriminate on the basis of sex for any reason. - False
ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii ii
The American with Disabilities Act of 1990 requires employers to make a reasonable
ii ii ii ii ii ii ii ii ii ii ii ii ii
accommodations to suit the needs of disabled applicants. - True
ii ii ii ii ii ii ii ii ii ii ii ii
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller STUVATE. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $10.99. You're not tied to anything after your purchase.