m2-Which of the following is not a construction schedule milestone: a) submittal approval b) Project Delivery and team selection process c) Procurement (Bidding/negotiating/purchasing) Activities. d) Contract Completion - ANSWERSProje...
CDT Practice Study Guide Exam
Questions & Answers 2024/2025
m2-Which of the following is not a construction schedule milestone: a) submittal approval b) Project
Delivery and team selection process c) Procurement (Bidding/negotiating/purchasing) Activities. d)
Contract Completion - ANSWERSProject Delivery and team selection process
m6-If a date to proceed is not stipulated in the agreement, the owner should issue to the contractor a: -
ANSWERSNotice to Proceed
m6-Pre-construction Activities Begin when the contractor has receivedL - ANSWERSA Letter of Intent to
Award
m6-Which of the following is not a mobilization and Start up cost - ANSWERSRoyalties, Licenses and Fees
m6-It is important to establish the site conditions prior to: - ANSWERSmobilization
m6-Mobilization typically occurs after: - ANSWERSReceipt of a notice to proceed and following a
reconstruction meeting
m6-Which two types of bonds might be required during construction - ANSWERSPerformance Bond and
Bid Bond
m6-Inspections are done by the AHJ to determine if the construction complies with - ANSWERSCodes
and Regulations
m6-The contractor Should being Preparation and Delivery for the Pre-construction Submittals after
which Event - ANSWERSExecution of Agreement
m6-Payment and Performance bonds are which type of document - ANSWERSPre-construction Submittal
, m6-It is important for subcontract and purchase order documents to reference the - ANSWERScontract
documents
m6-Which two Parties are responsible for submittal of a set of construction documents tot he AHJ for
permit review - ANSWERSOwner and Architect
m6-What is typically the contractor's first activity on the project site - ANSWERSMobilization
m7According to the AIA A201 The contractor has sole responsibility and control over the following
construction activities - ANSWERSMeans, methods, techniques, sequences, procedures, coordination,
job site safety
m7The responsibility of inspecting work already performed for proper conditions to receive subsequent
work lies with the - ANSWERSContractor
M7- The contractor's superintendent: - ANSWERSCan not be changed without the owners consent and
communication is as binding as if given by the contractor
m7- True or False - by executing the contract the contractor confirms that the contract time is reasonable
- ANSWERSTrue
m7- The date of substantial completion is established by the - ANSWERSA/E
`m7- Under A201 who has the responsibility to pay sales, consumer, use and similar taxes for the work
provided? - ANSWERScontractor
m-7If the contractor is delayed in the progress of the work by the owner the contractor should: -
ANSWERSWrite the A/E requesting a change order granting an extension of time.
m7- Product equivalency, manufacturer, installation, operating cost, maintenance costs, and warranty
are major factors to be considered for: - ANSWERSSubstitution Request
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Bensuda. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $8.99. You're not tied to anything after your purchase.