100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
TEST ACQ 202 Module 4 Exam Part II Developing the System Spring 2024 Defense Acquisition University $25.99   Add to cart

Exam (elaborations)

TEST ACQ 202 Module 4 Exam Part II Developing the System Spring 2024 Defense Acquisition University

 11 views  0 purchase
  • Course
  • Institution

TEST ACQ 202 Module 4 Exam Part II Developing the System Spring 2024 Defense Acquisition University

Preview 3 out of 28  pages

  • June 14, 2024
  • 28
  • 2023/2024
  • Exam (elaborations)
  • Questions & answers
  • Unknown
avatar-seller
TEST ACQ 202 Module 4 Exam Part II Developing the System



1. What is your assessment about a program with a Schedule
Performance Index (SPI) of 1.1?
Answer: The contractor is accomplishing the work more
efficiently than expected.

2. Which of the following is FALSE?
Answer: Exit criteria are not specific to a particular phase of an
acquisition program.

3. A (n) ______ can be used for predicting program obligation
performance and funding requirements and identifying potential
budget execution problems.
Answer: Spending Plan

4. An operational test agency is responsible for the establishment of
Critical Operational Issues (COIs). True or False
Answer: True

5. The following data is received from your contractor: Budgeted
Cost of Work Performed (BCWP)=$300 Cost Performance Index
(CPI)=1.2 Budgeted Cost of Work Scheduled (BCWS)=$400…
Answer: EAC Low: $833 EAC High: $1,028

6. Spending plans serve as a tool to analyze program execution, an
indicator of potential problems, and a predictor of future program
performance. True or False
Answer: True

7. Which of the following is a valid reason for rebaselining the
Performance Measurement Baseline (PMB)

This study source was downloaded by 100000863832091 from CourseHero.com on 04-17-2024 07:54:15 GMT -05:00


https://www.coursehero.com/file/34762760/AA-TEST-ACQ-202-Module-4-Exam-Part-II-Developing-the-Systemdocx/

, Answer: The plan for completing the remaining contract effort is
no longer achievable?

8. With modeling and simulation, we model the system and then
test the __________ to gather test predictions
Answer: Model

9. What type of testing would be conducted to determine the
effectiveness of the manufacturing process?
Answer: Production Qualification Testing (PQT)

10. The Comptroller’s administrative reservation of funds for a
specific purpose is referred to as a (n):
Answer: Commitment

11. Which of the following test items are determined by the
Program Management Office that is developing the system?
Answer: Critical Technical Parameters (CTPs)

12. The following data is received from your contractor on a key
component of the project: Budgeted Cost of Work Performed
(BCWP)=300 Budgeted Cost of Work Scheduled (BCWS)=$200
Actual Cost of Work Performed (ACWP)=$500. Which of the
following Earned Value Management (EVM) metrics can be
determined from these data?
Answer: CV=- $200 and SV = $100

13. Which of the following statements is NOT true regarding the
requirements and objectives associated with an Integrated
Baseline Review (IBR)?




This study source was downloaded by 100000863832091 from CourseHero.com on 04-17-2024 07:54:15 GMT -05:00


https://www.coursehero.com/file/34762760/AA-TEST-ACQ-202-Module-4-Exam-Part-II-Developing-the-Systemdocx/

, Answer: The IBR is conducted exclusively by the Government and
contractor business management staff and technical staff are
rarely included.

14. With earned value management (EVM), the Government
can determine if a program is currently experiencing a/n _____.
Answer: Cost or schedule variance

15. Which test would a contractor conduct on a software item
before they integrate it with hardware?
Answer: Component Testing

16. What type of testing is performed to determine a weapon
system’s performance with respect to survivability and lethality?
Answer: Live Fire Test and Evaluation

17. What would operational testers use to determine whether a
system meets operational performance parameters?
Answer: Measures of Effectiveness




This study source was downloaded by 100000863832091 from CourseHero.com on 04-17-2024 07:54:15 GMT -05:00


https://www.coursehero.com/file/34762760/AA-TEST-ACQ-202-Module-4-Exam-Part-II-Developing-the-Systemdocx/

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller VEVA2K. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $25.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

79373 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$25.99
  • (0)
  Add to cart