VIRGINIA CONTRACTORS STUDY - A & B LICENSE (CALCULATION PART) exam with 100% correct answers
- Course
- Institution
The owner requests changes which will cost the contractor $2,500 in labor and materials and $700 in overhead costs. With the change, the contractor would be relieved of $1,000 in labor costs and $280 in overhead costs from the original contract. The original bid included profit of 10% of all costs....