CSI CDT Exam Study Guide (questions and answers) 100% solved Owner - CORRECT ANSWER -Principle stakeholder - initiates project, assumes risk, provides funding AHJ - Authorities Having Jurisdiction - CORRECT ANSWER -Protect public health, safety and welfare Design Team - CORRECT ANSWER -Address planning issues, determine design program, identify codes and regulations, produce procurement and construction documents, administer construction contract, *provide QA/QC procedures* Contractor Team - CORRECT ANSWER -Entity that constructs a facility. Uses management abilities to gather labor forces, subs, and material/product/equipment suppliers Supplier Team - CORRECT ANSWER -Furnishes the materials and products for the facility to be constructed. Fabricator, Distributor, Manufacturer, Supplier. Facility Life Cycle - CORRECT ANSWER -The life cycle of a facility, from concept through construction to use and eventual deconstruction. Project Conception Project Delivery Design Construction Documents Procurement (Bidding/Negotiating/Purchasing) Construction Facility Management Project Conception - CORRECT ANSWER -Transforms the needs of owner into clear concept on which project can be designed. Feasibility Study, Programming, Site Selection, Budgeting. Project Delivery - CORRECT ANSWER -Determine delivery method to be used. Factors - qualifications, experience, capacity, project extent, time requirements. Design - CORRECT ANSWER -Two Phases: schematic design and design development. Deliverables include graphic and written design documents and estimates of project cost. Schematic Design - CORRECT ANSWER -Overall relationships and functions. Site plan and area, general size/shape/massing of elements, elevations and exteriors established, conceptual design criteria identified. Deliverables - schematic drawings, probable cost, preliminary schedules Design Development - CORRECT ANSWER -Technical issues of constructibility and integration of systems and components. Deliverables - Tech information, outline specifications, updated schedule, updated cost estimate. Construction Documents - CORRECT ANSWER -Defined as the written and graphic documents prepared or assembled by the A/E for communicating the project design for construction and administering the construction contract. Construction documents include two majo r types of documents: Procurement documents and Contract documents. Procurement (Bidding/Negotiating/Purchasing) - CORRECT ANSWER -Acceptance of the contractor's bid or negotiated sum and other conditions will result in award of a contract and commencement of work. Construction - CORRECT ANSWER -Responsibilities: Contractor - perform work, project coordination, comply with project documents. A/E - construction admin, evaluation services, certify application for payment, final inspection of work. Owner - provide information, process payments, approve contract modifications, accept project upon completion. Facility Management - CORRECT ANSWER -During occupancy, owners & facility managers maintain and evaluate the performance of the project and determine suitability for continuing use. OmniClass - CORRECT ANSWER -A multi -table informational framework for organizing information used by the architectural, engineering, and construction industry. UniFormat - CORRECT ANSWER -Uniform classification system for organizing preliminary construction information into a standard order or sequence on the basis of systems or assemblies. Particularly useful in conceptual design. Element Identification. MasterFormat - CORRECT ANSWER -Arranges related construction practices, logical groupings of work results, into a series of divisions. 50 division format. Used for Specifications, data organization, and cost classification. MasterFormat Groups - CORRECT ANSWER -00 Procurement and Contracting Requirement Group Specifications Group