Which of the following defects requires repair?
A. A loose door gasket
B. A bent J-bar that does not affect door operation
C. A dent 13mm (1/2 in) deep on the door sill
D. Four dents, ea...
IICL CONTAINER INSPECTOR’S EXAM
WITH QUESTIONS AND WELL
VERIFIED ANSWERS [GRADED A+]
ACTUAL 100%
Which of the following defects requires repair?
A. A loose door gasket
B. A bent J-bar that does not affect door operation
C. A dent 13mm (1/2 in) deep on the door sill
D. Four dents, each 11mm (7/16 in) deep, on contiguous outboard
corrugations of a roof panel - ANS✔✔---A. A loose door gasket
Of the following conditions in a dry-van container, which one would require
cleaning?
A. Raised mud foot prints in excess of what might normally remain after a
sweep out
B. Dry dust covering dried floor stains as might normally be found after a
sweep out
C. Coffee beans remaining inside the container as might occur after a sweep
out
D. Polyurethane beads as might be expected to lodge in grooves between
floorboards after a sweep out - ANS✔✔---C. Coffee beans remaining inside
the container as might occur after a sweep out
,The top of a replacement plastic ventilator should be centered what distance
from the top side rail? A. 50-55mm (2-2 3/16 in) B. 70-75mm (2 5/8 - 3 in)
C. 100mm (4in) D. 150mm (6 in) - ANS✔✔---A. 50-55mm (2-2 3/16 in)
When must a reference line extend the full length of a bottom side rail? A.
When there are two or more areas of damage on the bottom side rail B. When
there is a sharp bend in the bottom side rail
C. When there is a bowing over the entire bottom side rail D. When there is
additional damage to the bottom side rail so that the reference line cannot
be positioned over the ends of the damage - ANS✔✔---C. When there is a
bowing over the entire bottom side rail
Which of the following is NOT a transverse structural member of the
container?
A. Front sill B. Tunnel rail
C. Rear header
D. Crossmember - ANS✔✔---B. Tunnel rail
An Equipment Interchange Receipt (EIR), based on an inspection with no
damage found, can be evidence of a container's compliance with: A.
Australian Timber Component Treatment Regulations B. Convention for Safe
Containers (CSC) regulations through the ACEP Program
C. Transport under custom's seal (TIR) regulations D. International Standards
Organization (ISO) CEDEX codes regulations - ANS✔✔---B. Convention for
Safe Containers (CSC) regulations through the ACEP Program
A steel corner fitting is being replaced. To ensure better weld penetration,
IICL recommends that the edges of parts adjacent to the corner fitting be
ground to a minimum bevel of? A. 30 degrees B. 45 degrees
C. 55 degrees D. 60 degrees - ANS✔✔---B. 45 degrees
Which of the following components is sometimes placed longitudinally in the
container to support plywood flooring? A. Transverse bow B. Gusset
, C. Hat section center spacer
D. Threshold plate - ANS✔✔---C. Hat section center spacer
Which of the following is an example of a plank floor condition requiring
repair AND which should be considered as damage?
A. A crack or split with no evidence of impact, which leaks light
B. A crack or split with a sign of impact which does not leak light
C. A crack or split, adjacent to a dented bottom rail, which leaks light
D. A crack or split, with no evidence of impact, with a loose piece - ANS✔✔-
--C. A crack or split, adjacent to a dented bottom rail, which leaks light
Welds to corner fittings should be made with?
A. CO2 semi-automatic welding
B. Low hydrogen welding rods
C. Fully automatic welding
D. Arc welding - ANS✔✔---B. Low hydrogen welding rods
All of the following procedures are required EXCEPT
A. Weld smoke, spatter, etc. must be removed to permit adhesion of paint
B. The damaged component(s) must be restored as close as possible to
original size and profile
C. Welds must be examined using radiographic or magnetic particle non-
destructive testing equipment
D. Replacement steel components must be painted with coating compatible
with that originally applied to the container - ANS✔✔---C. Welds must be
examined using radiographic or magnetic particle non-destructive testing
equipment
Where should the reference line be placed in order to determine
repairworthiness of a crossmember flange that is bent upwards?
A. Along the inside lower formed edge of the crossmember
B. Spaced out from the crossmember web
C. On the outermost flange surface along the full crossmember length
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller jackwa. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $18.99. You're not tied to anything after your purchase.