Exam (elaborations)
VA Contractors VA Advanced (Class A) Actual Questions with 100% Correct Answers | Updated | Download to score A+
- Course
- Institution
1. A lump sum contract on a project has a total contract price of $160,000. Retainage has been held back at 10%. The contractor has received progress payments for 75% of the project. The contractor submits a request for final payment for the new completed project. The final payment amount should be...
[Show more]