A contractor wants to raise the car speed from 100 fpm to 125 fpm, it currently has a 12" sheave. What is required? - Answer 100 fpm/125 fpm= 12"/ X =15 A MOV (Metal Oxide Varistor) burns out. You replace it, but cannot read voltage or resistance. What should you do? - Answer Replace it with...