Final Assessment Nerc Exam 100% Correct Answers When using a dynamic schedule and the energy profile in an hour is >250 MW and the actual hourly integration deviates from the hourly energy profile by ____ the tag must be modified. A. 100 MW B. 10% C. 50 MW D. 25% - Correct Answer B. 10% ...