Test Bank For Project Management in Practice, 7th Edition Meredith Chapter 1-8 .A+ Chapter 1: The World of Project Management True/False 1. A primary purpose of forming projects is to assign the responsibility for accomplishing some organizational task to a specific person or small group. Answ...

[Show more]

Preview 4 out of 138  pages

  • March 23, 2024
  • 138
  • 2023/2024
  • Exam (elaborations)
  • Questions & answers
avatar-seller
Test Bank For
Project Management in Practice, 7th Edition Meredith
Chapter 1-8

Chapter 1: The World of Project Management
True/False
1. A primary purpose of forming projects is to assign the responsibility for
accomplishing some organizational task to a specific person or small group.

Answer: True
Response: See section 1.1
Level: easy



2. One of the few similarities between project management and general management
is that both exist in the well-defined organizational structure of
superior/subordinates in the overall organization.

Answer: False
Response: See section 1.2
Level: medium



3. Many recent developments in project management are being driven by changes in
the nature of the American workforce.

Answer: False
Response: See section 1.1
Level: medium



4. There has been a growing use of projects to achieve an organization’s strategic
goals

Answer: True
Response: See section 1.1
Level: medium




Copyright ©2017 John Wiley & Sons, Inc.

,5. While general managers have their authority limited to specific areas in the
overall organization, project managers have authority over any activity required
by the project.

Answer: False
Response: See section 1.2
Level: medium



6. Projects are always carried out under conditions of uncertainty.

Answer: True
Response: See section 1.3
Level: easy



7. One can trade-off time and cost when managing a project, but the project’s
technical specifications must be maintained exactly as the client initially specifies.

Answer: False
Response: See section 1.3
Level: medium



8. Nonnumeric project selection methods are only suitable if numeric methods are
not available.

Answer: False
Response: See section 1.5
Level: medium


9. When using financial methods for selecting projects, the payback period is the
simplest and best method to use.

Answer: False
Response: See section 1.5
Level: medium



10 Rank-ordering a large number of projects can be done with a Q-sort.



Copyright ©2017 John Wiley & Sons, Inc.

, Answer: True
Response: See section 1.5
Level: medium



11. A disadvantage of using the payback period method for selecting projects is that it
cannot reflect the time-value of money.

Answer: True
Response: See section 1.5
Level: medium




12. A disadvantage of using the discounted cash flow method (or net present value)
for selecting projects is that it ignores all non-monetary factors associated with the
project except risk.

Answer: True
Response: See section 1.5
Level: medium



13. A disadvantage of using scoring models rather than financial models for selecting
projects is that they cannot include the project’s profitability.

Answer: False
Response: See section 1.5
Level: medium



14. A PM does not need to understand why a project is selected for funding because
he did not initiate the process.

Answer: False
Response: See section 1.5
Level: medium



15. The main distinction between platform and breakthrough projects is that the
former usually depend on existing technology.


Copyright ©2017 John Wiley & Sons, Inc.

, Answer: True
Response: See section 1.6
Level: medium



16. The main distinction between platform and derivative projects is that the latter
depend on existing technology.

Answer: False
Response: See section 1.6
Level: medium




17. One reason for the emphasis on project management is that tasks fit neatly into
business-as-usual.

Answer: False
Response: See section 1.1
Level: easy



18. Programs are subdivisions of projects.

Answer: False
Response: See section 1.1
Level: easy



19. Projects are subdivisions of programs.

Answer: True
Response: See section 1.1
Level: easy



20. A similarity between project management and general management is the
tendency to ―manage by exception.‖


Copyright ©2017 John Wiley & Sons, Inc.

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller TestsBanks. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $12.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

82871 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$12.99
  • (0)
  Add to cart