QSP COURSE QUESTIONS AND CORRECT ANSWERS When is receiving water monitoring required for a risk level 3 site? - ANSWER-When there is a direct discharge to receiving waters* and effluent is outside the pH range of 6.0-9.0 or turbidity exceeds
- Course
- Institution
QSP COURSE QUESTIONS AND CORRECT ANSWERS When is receiving water monitoring required for a risk level 3 site? - ANSWER-When there is a direct discharge to receiving waters* and effluent is outside the pH range of 6.0-9.0 or turbidity exceeds 500 NTU. Which risk level/type may be required t...