A project estimator is developing a cost estimate for construction of a new diagnostic imaging wing. The projected costs are: Fixed equipment installation charges $700,000 Site isolation $50,000 Annual utilities $425,000 Construction materials $1,200,000 Portable equipment $900,000 Annual de...