PMI (PMP) Exam 6th Edition PMBOK | Questions Bank | 928 Questions with 100% Correct Answers
0 view 0 purchase
Course
PMI
Institution
PMI
An element of the project scope statement is:
A. Acceptance criteria.
B. A stakeholder list.
C. A summary budget.
D. High-level risks. Correct ans - A
Reserves Analysis Correct ans - Risk management method of determining contingency or management reserves for schedule...
PMI (PMP) Exam 6th Edition PMBOK | Questions Bank | 928
Questions with 100% Correct Answers | with COMPLETE SOLUTION
[230 PAGES]
An element of the project scope statement is:
A. Acceptance criteria.
B. A stakeholder list.
C. A summary budget.
D. High-level risks. Correct ans - A
Reserves Analysis Correct ans - Risk management method of
determining contingency or management reserves for schedule
Which document describes the necessary information to determine if a
project is worth the required investment?
A. Cost baseline
B. Service level agreement
C. Memorandum of understanding
D. Business case Correct ans - D
Which input to the Plan Risk Management process provides information on
high-level risks?
A. Project charter
B. Enterprise environmental factors
C. Stakeholder register
D. Organizational process assets Correct ans - A
Which item is an example of personnel assessment?
A. Resource calendar
B. Tight matrix
C. Team-building activity
D. Focus group Correct ans - D
Which input to the Manage Stakeholder Engagement process provides
guidance on how stakeholders can best be involved in a project?
A. Feedback analysis
B. Stakeholder analysis
C. Communication management plan
D. Stakeholder management plan Correct ans - D
,Which input to the Identify Stakeholders process provides information about
internal or external parties related to the project?
A. Procurement documents
B. Communications plan
C. Project charter
D. Stakeholder register Correct ans - C
The Identify Stakeholders process is found in which Process Group?
A. Initiating
B. Monitoring and Controlling
C. Planning
D. Executing Correct ans - A
An input to Develop Project Charter is a/an:
A. Business case.
B. Activity list.
C. Project management plan.
D. Cost forecast. Correct ans - A
Which Knowledge Area involves identifying the people, groups, or
organizations that may be impacted by or impact a project?
A. Project Risk Management
B. Project Human Resource Management
C. Project Scope Management
D. Project Stakeholder Management Correct ans - D
Which input to Collect Requirements is used to identify stakeholders who can
provide information on requirements?
A. Stakeholder register
B. Scope management plan
C. Stakeholder management plan
D. Project charter Correct ans - A
In which Knowledge Area is the project charter developed?
A. Project Cost Management
B. Project Scope Management
C. Project Time Management
D. Project Integration Management Correct ans - D
The ability to influence cost is greatest during which stages of the project?
,A. Early
B. Middle
C. Late
D. Completion Correct ans - A
Which process involves developing an approximation of the monetary
resources needed to complete project activities?
A. Estimate Costs
B. Control Costs
C. Determine Budget
D. Plan Cost Management Correct ans - A
Which tool or technique is used in the Develop Project Management Plan
process?
A. Pareto diagram
B. Performance reporting
C. SWOT analysis
D. Expert judgment Correct ans - D
The organization's perceived balance between risk taking and risk avoidance
is reflected in the risk:
A. Responses
B. Appetite
C. Tolerance
D. Attitude Correct ans - A
An output of the Manage Stakeholder Engagement process is:
A. change requests
B. enterprise environmental factors
C. the stakeholder management plan
D. the change log Correct ans - A
Which process numerically analyzes the effect of identified risks on overall
project objectives?
A. Plan Risk Management
B. Plan Risk Responses
C. Perform Quantitative Risk Analysis
D. Perform Qualitative Risk Analysis Correct ans - C
Which Collect Requirements output links the product requirements to the
deliverable that satisfy them?
, A. Requirements documentation
B. Requirements traceability matrix
C. Project management plan updates
D. Project documents updates Correct ans - B
A temporary endeavor that creates a unique product or service is called a:
A. Project
B. Plan
C. Program
D. Portfolio Correct ans - A
The process of prioritizing risks for further analysis or action is known as:
A. Plan Risk Management.
B. Plan Risk Responses.
C. Perform Qualitative Risk Analysis.
D. Perform Quantitative Risk Analysis. Correct ans - C
Stakeholder satisfaction should be managed as a key project:
A. Benefit
B. Initiative
C. Objective
D. Process Correct ans - C
Which cost is associated with nonconformance?
A. Liabilities
B. Inspections
C. Training
D. Equipment Correct ans - A
Identify Risks is part of which Process Group?
A. Planning
B. Executing
C. Closing
D. Initiating Correct ans - A
The business needs, assumptions, and constraints and the understanding of
the customers needs and high-level requirements are documented in the:
A. Project management plan.
B. Project charter.
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller THEEXCELLENCELIBRARY. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $26.39. You're not tied to anything after your purchase.