PJM Sample TO Exam Questions & Answers 2024 What is the minimum notice PJM requires for a nonemergency transmission outage work request which does not cause congestion? A. 48 hours B. First day of month proceeding the month of the outage C. 5 working days D. 1 week - ANSWER-B. First day of...